12 Mile Road | Lahser Road to Evergreen Road | Southfield | Reconstruction of road including asphalt paving, traffic signal upgrades, adding right-turn lanes at several locations, Americans with Disabilities Act-compliant crosswalks, pathway construction and new curb and gutter. | No. Two-way traffic maintained. | No | M.L. Chartier Excavating, Inc. | 5/24 | Late October | 12 Mile Road, Lahser to Evergreen |
*12 Mile Road-westbound lanes only (PERMIT PROJECT) | Stephenson Highway to Edgeworth Avenue | Royal Oak and Madison Heights | Consumers Energy gas main work. | Yes, only westbound 12 Mile is closed. | Westbound traffic detour is Stephenson Hwy to 13 Mile Rd to Campbell Rd, back to 12 Mile Rd. | Consumers Energy | 6/23 | 7/6 | Consumers Energy |
14 Mile Road (PERMIT PROJECT) | West of Decker/Novi Road | Commerce Township, Novi and Walled Lake | Great Lakes Water Authority watermain replacement. | Yes. 14 Mile Rd is closed just west of Decker/Novi Rd. | Pontiac Trail to Maple Rd to M-5, back to 14 Mile Rd and vice versa. | Great Lakes Water Authority | 1/4 | Late Summer | Permit Work & Short-Term Road Closures |
*Adams Road | Long Lake Road to Square Lake Road | Troy and Bloomfield Township | Resurfacing with asphalt; upgrade to Long Lake/Adams Rd traffic signal; new center, left-turn lanes at Vineyards Dr. and Westview Rd; Americans with Disabilities Act-compliant crosswalks; improved drainage; extension of some passing and right-turn lanes. | Yes, southbound Adams Rd is expected to close to through traffic on June 28, northbound Adams Road will remain open for local traffic only. | Southbound traffic detour is Adams Rd to Square Lake Rd to Coolidge Hwy to Long Lake Rd, back to Adams Rd. | Pro-Line Asphalt | 6/14 | Late October | Adams Road |
Barron Road | Grange Hall Road to just north of Groveland Road | Groveland Township | Paving 2.39 miles of gravel road with asphalt, improved drainage, concrete curbs and gutters. | Yes. Residential and business access maintained. | Grange Hall Rd to Jossman Rd to Groveland Rd, back to Barron Rd and vice versa. | Iafrate Construction | 4/12 | Early November | Barron Road |
Big Beaver Road | Rochester Road to Dequindre Road | Troy | Concrete slab replacement | No. Expect lane closures on westbound Big Beaver Road for the work. Once completed, work continues on eastbound Big Beaver Road with lane closures. | No. | DiLisio Contracting | 5/6 | Fall, TBA | Concrete Slab Replacements |
Big Beaver Road (PERMIT PROJECT) | Just west of Dequindre Road (westbound lanes) | Troy | City of Troy watermain and sanitary sewer work. | No. Westbound Big Beaver Road will have lane closures just west of Dequindre Road (one lane will remain open for traffic during the work). | No | Pamar Enterprises | 4/19 | Early August | City of Troy Construction Updates |
*Clarkston Road | Clearview Drive to Eston Road | Independence Township | High-Friction Surface Control application to the road curves to improve vehicle traction and safety. | No, flaggers will direct traffic in the work zone. | No. | Smith's Waterproofing | 6/28 | 7/2 | High-Friction Surface Treatment |
Concrete Slab Replacements | Various heavier traveled roads throughout Oakland County | Various | Remove and replace concrete. | No, expect lane closures and traffic delays. | No | DiLisio Contracting and Cipparrone Contracting | 4/9 | Fall, TBA | Concrete Slab Replacements |
Cranbrook Road | 14 Mile Road to Maple Road | Bloomfield Township and City of Birmingham | Resurfacing 1.2 miles of road with asphalt, safety improvements, Americans with Disabilities Act-compliant sidewalk ramp improvements, traffic-signal upgrades, new curb and gutter. | Yes. Local access to homes, businesses and Seaholm High School maintained. | For Cranbrook Rd through traffic: 14 Mile Rd to Lahser Rd to Maple Rd, back to Cranbrook/ Covington Rd and vice versa. For Lincoln Rd through traffic: Southfield Rd to Maple Rd and vice versa. | Pro-Line Asphalt | 6/14 | Late August | Cranbrook Road |
Currie Road | 9 Mile Road to 10 Mile Road | Lyon Township | Gravel road paving (with asphalt) project that includes improved drainage, intersection improvements at Currie/10 Mile Road and new curbs and gutters. | Yes | 10 Mile Rd to Napier Rd to 9 Mile Rd, back to Currie Rd and vice versa. | Iafrate Construction | 4/12 | Early October | Currie Road |
Eston Road (part of the Independence Township road funding millage) | Clarkston Road to Algonquin Blvd. | Independence Township | Culvert removal and replacement just north of Alamo Avenue. Additionally, road will be milled and paved with asphalt as part of the Independence Township road funding millage. Paving work does not include the gravel section of the road. | Yes; however, local traffic will be maintained north and south of Alamo Avenue (location of culvert removal and replacement). | Clarkston Rd to Baldwin Rd to Indianwood Rd, back to Eston Road and vice versa. | Cadillac Asphalt | 6/1 | Late July | Independence Township Road Funding Millage |
Flemings Lake Road and Walters Road (part of the Independence Township road funding millage) | Clarkston Road to Waldon Road | Independence Township | Removal of the current pavement, grading/gravel work on the road’s base and paving with asphalt. | Yes. Residential access will be maintained. | Clarkston Rd to Sashabaw Rd to Waldon Rd and vice versa. | Cadillac Asphalt | 6/21 | Late July | Independence Township Road Funding Millage |
Grand River Avenue/Novi Road intersection | Grand River Avenue/Novi Road intersection | Novi | Concrete repairs, traffic signal upgrade, Americans with Disabilities Act-compliant crosswalks, some new curb and gutter. | Yes. Grand River Ave is closed from Crescent Blvd and Novi Rd (west leg) for stage one construction. Stage two involves closing Grand River Ave from Novi Rd to Towne Center Dr (date TBA) | NB and SB Novi Rd at Grand River Ave remains open to traffic with lane restrictions. Detour for the Grand River Ave stage one closure from Crescent Blvd to Novi Rd is Crescent Blvd to Towne Center Dr, back to Grand River Ave. | DiLisio Contracting | 6/14 (expected closure date) | Early September (for completion of entire project) | Concrete Slab Replacements |
Greenfield Road (PERMIT PROJECT) | 13 Mile Road to 14 Mile Road | Beverly Hills and Royal Oak | Consumers Energy gas main replacement work. | Yes, the road is closed to through traffic. Northbound Greenfield Road is open to local traffic only. Residential and business access maintained. | 13 Mile Rd to Southfield Rd to 14 Mile Rd, back to Greenfield Rd and vice versa. | Consumers Energy | 5/10 | Late July | Permit Work & Short-Term Road Closures |
*Hickory Ridge Road | Commerce Road to General Motors Road | Milford Township | Remove and replace culverts under the road. The culverts are located on Hickory Ridge Road just north and south of General Motors Road. Crews will remove the culvert just north of General Motors Road first. | Yes, culverts are just north and south of General Motors Road. Residential and business access maintained. | Commerce Rd to Pleasant Valley/Kensington Rd to Stobart Rd, back to Hickory Ridge Rd and vice versa. | RCOC Highway Maintenance | 6/26 (work is weather-dependent and could be delayed until 6/27) | 6/26 (evening) | Permit Work & Short-Term Road Closures |
Mann Road (PERMIT PROJECT) | Clintonville Road to Sunburst Avenue | Independence Township | Sanitary sewer installation for a private development. | Yes, business and residential access maintained. | Lake Angelus Rd to Rohr Rd, back to Mann Rd and vice versa. | Pamar Enterprises | 6/7 | Early July | Permits & Short-Term Road Closures |
Maple Road | Franklin Road to Inkster Road | Bloomfield Township | Resurfacing, improved drainage, new traffic signals, addition of a center left-turn lane (from Inkster to east of Norham Rd), new curb/gutter, culvert replacement east of Norham Rd and pathway construction on north side of Maple Rd. | Yes, residential and business access maintained. | Inkster Rd to Walnut Lake Rd to Franklin Rd, back to Maple Rd and vice versa. | Dan's Excavating | 4/8 | Late September | Maple Road |
Maple Road (PERMIT PROJECT) | Middlebelt Road to Orchard Lake Road | West Bloomfield Township | Consumers Energy pipeline work. | No, there are lane and road-shoulder closures. Additionally, flaggers will direct traffic when necessary. | No | Michels Corporation | 4/15 | Late August | Consumers Energy |
Middlebelt Road (PERMIT PROJECT) | 13 Mile Road to Maple Road | Farmington Hills and West Bloomfield Township | Consumers Energy pipeline work. | No, there are lane and road-shoulder closures. Additionally, flaggers will direct traffic when necessary. | No | Michels Corporation | 4/15 | Late August | Consumers Energy |
Orchard Lake Road | Just south of 11 Mile Road to I-696 | Farmington Hills | Remove and replace concrete. | No, expect lane closures during the work. Access to businesses and side streets will be maintained during the work. | No | Cipparrone Contracting | 6/14 | August (TBA) | Concrete Slab Replacements |
Preservation Overlays (Simple Resurfacing) | Various heavier traveled roads throughout Oakland County | Various | Simple resurfacing with placing 2-2.5 inches of asphalt on the road surface; work is weather-dependent. | No, expect traffic delays. | No | Cadillac Asphalt and Ace-Saginaw Paving | 5/11 | Fall, TBA | 2021 Project List |
Sashabaw Road and Oakhill Road Roundabout | Sashabaw Road and Oakhill Road intersection | Brandon and Independence townships | Construction of a compact roundabout, reconstruction of one-third mile of roadway with asphalt, improved drainage, Americans with Disabilities Act-compliant crosswalks, lighting and new curbs and gutters. | Yes | Sashabaw Rd detour: Seymour Lake Rd to Baldwin Rd to Clarkston Rd, back to Sashabaw. Oakhill Rd detour: Perry Lake Rd to Seymour Lake Rd to Dartmouth Rd back to Oakhill Rd | TBA | Summer of 2021 | Fall, TBA | Oakhill/Sashabaw Road Compact Roundabout |
*South Hickory Ridge Road (PERMIT PROJECT) | M-59 (Highland Road) to Lone Tree Road | Highland Township | ITC utility pole replacements. | Starting June 28, road will be under flag control for the initial work. Starting July 12, the road will close to through traffic. Residential and business access maintained. | M-59 (Highland Rd) to Milford Rd to Lone Tree Rd, back to South Hickory Ridge Rd and vice versa. | ITC | 6/28 (road will close to through traffic on July 12 through July 15) | 7/15 | Permit Work & Short-Term Road Closures |
Spot Resurfacing
| Various heavier traveled roads throughout Oakland County
| Various
| Milling (grinding of pavement) on smaller sections of roads and paving with asphalt. Work is weather-dependent.
| No.
| No
| Pro-Line Asphalt and Florence Cement
| 5/11
| COMPLETE | 2021 Project List |
Subdivision Roads (Special Assessment District) | Various subdivision roads in Oakland County townships | Various townships | Reconstruction and resurfacing roads with asphalt. | No | No | Various | Various start dates | Late fall | Special Assessment District (SAD) Projects |
*Union Lake Road | Wise Road to Willow Road | Commerce Township | Removal and replacement of a culvert under the road. Work include asphalt paving, storm sewer installation, new guardrail and signage. | Yes, business access maintained. Union Lake Rd will completely close just north of Willow Rd. | Wise Rd to Carroll Lake Rd to Commerce Rd, back to Union Lake Rd and vice versa. | V.I.L. Construction | 7/22 (tentatively) | Late September | Union Lake Road Culvert Replacement |
Walton Blvd. | Dixie Hwy to east of Sashabaw Road | Waterford Township | Reconstruction of road including asphalt paving, upgrading traffic signal, Americans with Disabilities Act-compliant crosswalks and new curb. | No. Currently, two-way traffic is maintained on Walton Blvd. from Dixie Hwy. to east of Sashabaw Rd. The north half of the Sashabaw Rd/Walton Blvd. intersection will close at a future date for paving. | No (the north half of the Sashabaw/Walton Blvd. intersection will close for paving at future date that will be announced) | Pro-Line Asphalt | 4/19 | Early fall | Walton Blvd. |