Independence Township Road Improvement Millage
Independence Township voters passed a road millage in 2018. The four-year millage provides funding to resurface virtually every major road in the township. This page provides a list of roads that will be improved.
Resurfacing projected schedule for 28.4 miles of roads:
2021:
In 2021, 9.36 miles of heavier traveled road in Independence Township will be resurfaced at an estimated cost of $6.24 million. Dates for each project will be announced.
- Clarkston Road, from the Village limits to the Orion Township border
- Flemings Lake/Walters Road, from Clarkston Road to Waldon Road
- North Eston Road, from Clarkston Road to pavement end
- White Lake Road, from the Village limits to Andersonville Road
2021 CONTRACTOR: Cadillac Asphalt WEBSITE: https://www.cadillacasphalt.com/
2022:
- Holcomb Road, from the Village limits to the Springfield Township border
- Maybee Road, from Dixie Hwy to the Orion Township border
Independence Township Road Improvement Millage Information: CLICK HERE Version OptionsIndependence Township Road Improvement Millage Headline to learn more about Independence Township Road Improvement Millage Information: to learn more about Independence Township Road Improvement Millage Information: to learn more about Independence Township Road Improvement Millage Information: to learn more about Independence Township Road Improvement Millage Information:
RCOC Praises Community Road Millage Efforts: CLICK HERE Version OptionsIndependence Township Road Improvement Millage Headline to learn more about RCOC Praises Community Road Millage Efforts: to learn more about RCOC Praises Community Road Millage Efforts: to learn more about RCOC Praises Community Road Millage Efforts: to learn more about RCOC Praises Community Road Millage Efforts:
Completed work:
2020 work completed:
- Andersonville Road,from Old White Lake Road to the township border (May 8 start and expected completion late June) COMPLETE
- Clintonville Road, from Maybee Road to township line Mann Road (August 4 expected start) COMPLETE
- Clintonville Road, from Waldon Road to Clarkston Road COMPLETE to learn more about PRESS RELEASE: to learn more about PRESS RELEASE:
- Clintonville Road, from Maybee Road to Waldon Road (August 26 trough Sept. 23 and will include road closure to through traffic; residential and business access will be maintained) COMPLETE to learn more about PRESS RELEASE: to learn more about PRESS RELEASE:
- Sashabaw Road, from south of Clarkston Road (DTE) to Oak Hill Road (township limits) (June 29 is the start date) *temporary striping will be placed until work on Sashabaw Road over the Whipple Lake canal is completed. COMPLETE
- Sashabaw Road, from Maybee Road to the township border (July 13 expected start for resurfacing work; preliminary work begins July 9) COMPLETE
- Waldon Road, from the village limit to Clintonville Road (May 26 -early July, road closed to through traffic; residential and business access will be maintained) COMPLETE
- 2020 CONTRACTOR: Cadillac Asphalt Contractor website: https://www.cadillacasphalt.com/
to learn more about ase: to learn more about ase: to learn more about ase:
Additional information:
REVISED START DATE: 2020 Independence Road Millage paving set to begin May 8 with Andersonville Road
2020 Independence Township Road Millage paving set it begin May 11 starting with Andersonville Road