Maple Road, Inkster to Franklin Road
Project: Maple Road (2021 construction)
Project limits: Inkster Road to Franklin Road
Community: Bloomfield Township
Cost: $4.55 million. Eighty percent of the cost is will be paid with federal road funds. The remainder is split by the R.C.O.C., Bloomfield Township and Oakland County general government (through the Tri-Party Program). The pathway extension is fully funded by the township.
Project information:
Tree removal (December 2020)- Utility relocation will place over the winter and spring and is expected to be completed by June 1, 2021; Maple Road to close March 2-March 12 for continued utility work. CLICK HERE to learn more about Utility relocation will place over the winter and spring and is expected to be completed by June 1, 2021; Maple Road to close March 2-March 12 for continued utility work. to learn more about Utility relocation will place over the winter and spring and is expected to be completed by June 1, 2021; Maple Road to close March 2-March 12 for continued utility work. to learn more about Utility relocation will place over the winter and spring and is expected to be completed by June 1, 2021; Maple Road to close March 2-March 12 for continued utility work. to learn more about Utility relocation will place over the winter and spring and is expected to be completed by June 1, 2021; Maple Road to close March 2-March 12 for continued utility work. to learn more about Utility relocation will place over the winter and spring and is expected to be completed by June 1, 2021; Maple Road to close March 2-March 12 for continued utility work. to learn more about Utility relocation will place over the winter and spring and is expected to be completed by June 1, 2021; Maple Road to close March 2-March 12 for continued utility work. to learn more about Utility relocation will place over the winter and spring and is expected to be completed by June 1, 2021; Maple Road to close March 2-March 12 for continued utility work. to learn more about Utility relocation will place over the winter and spring and is expected to be completed by June 1, 2021; Maple Road to close March 2-March 12 for continued utility work. to learn more about Utility relocation will place over the winter and spring and is expected to be completed by June 1, 2021; Maple Road to close March 2-March 12 for continued utility work. to learn more about Utility relocation will place over the winter and spring and is expected to be completed by June 1, 2021; Maple Road to close March 2-March 12 for continued utility work. to learn more about Utility relocation will place over the winter and spring and is expected to be completed by June 1, 2021; Maple Road to close March 2-March 12 for continued utility work.
- Resurfacing with asphalt
- Addition of a center, left-turn lane from Inkster to east of Northam Road
- Upgrading right-turn lanes
- Extension of the pathway on the north side of Maple Road from Inkster to Westmoor Road (funded by the township), including the addition of Americans with Disabilities Act (ADA)-compliant crosswalks and upgraded pedestrian-crosswalk signals.
- Drainage improvements including ditch work and storm sewer installation.
- New curb and gutter
- Placement of new traffic signals, signs and pavement markings
- Culvert removal and replacement (located between Northam Road and Castle Drive)
Contractor: Dan's Excavating
End date: Late September
Road closure: Yes, expected to close on April 8 (residential and business access maintained)
Detour: Inkster Road to Walnut Lake Road to Franklin Road, back to Maple Road and vice versa.
Additional Information:
Maple Road to close for summer road work (Downtown Magazine)
Maple Road Project Information Flier
Maple Road from Inkster to Franklin Road to close Nov. 30-Dec 18 for utility relocation work (reopened to traffic on Dec. 11, 2020)