14 Mile Road (PERMIT PROJECT) | West of Decker/Novi Road and Decker/Novi Road to Welch Road | Commerce Township, Novi and Walled Lake | Great Lakes Water Authority watermain replacement | Yes. 14 Mile Rd is closed just west of Decker/Novi Rd. 14 Mile Rd from Decker/Novi Rd to Welch Rd is open to eastbound traffic only. | Pontiac Trail to Maple Rd to M-5, back to 14 Mile Rd and vice versa. | Great Lakes Water Authority | 1/4 | Late Summer | Permit Work & Short-Term Road Closures |
*Adams Road | Long Lake Road to Square Lake Road | Troy and Bloomfield Township | Resurfacing with asphalt, upgrade to Long Lake/Adams Rd traffic signal, new center, left-turn lanes at Vineyards Dr. and Westview Rd, Americans with Disabilities Act-compliant crosswalks, improved drainage, extension of some passing and right-turn lanes. | Yes, road will close to southbound traffic and remain open for northbound traffic only. | Southbound traffic detour is Adams Rd to Square Lake Rd to Coolidge Hwy to Long Lake Rd, back to Adams Rd. | TBA | Summer, TBA | Fall, TBA | Adams Road |
*Barron Road | Grange Hall Road to just north of Groveland Road | Groveland Township | Paving 2.39 miles of gravel road with asphalt, improved drainage, concrete curbs and gutters. | Yes. Additionally, Barron Rd just south of Groveland Rd will fully close for soil excavation starting May 3 through late May. Residential traffic will need to access property north and south of the closure. | Grange Hall Rd to Jossman Rd to Groveland Rd, back to Barron Rd and vice versa. | Iafrate Construction | 4/12 | Early November | Barron Road |
Big Beaver Road (PERMIT PROJECT) | Dequindre Road to John R (westbound lanes) | Troy | City of Troy watermain and sanitary sewer work. | No. Westbound Big Beaver Road will have lane closures (one lane will remain open for traffic during the work). | No | Pamar Enterprises | 4/19 | Late May | City of Troy Construction Updates |
Clarkston Road (part of the Independence Township road funding millage) | Sashabaw Road to Orion Township limits | Independence Township | Road resurfacing project. | No | No | Cadillac Asphalt | 4/19 | 6/14 | Independence Township Road Funding Millage |
Concrete Slab Replacements | Various heavier traveled roads throughout Oakland County | Various | Remove and replace concrete. | No, expect lane closures and traffic delays. | No | DiLiso Contracting and Cipparrone Contracting | 4/9 | Fall, TBA | Concrete Slab Replacements |
Cranbrook Road | 14 Mile Road to Maple Road | Bloomfield Township and City of Birmingham | Resurfacing 1.2 miles of road with asphalt, Americans with Disabilities Act-compliant sidewalk ramp improvements, traffic-signal upgrades, new curb and gutter. | TBA | TBA | Pro-Line Asphalt Paving | TBA | TBA | Cranbrook Road |
Currie Road | 9 Mile Road to 10 Mile Road | Lyon Township | Gravel road paving (with asphalt) project that includes improved drainage, intersection improvements at Currie/10 Mile Road and new curbs and gutters. | Yes | 10 Mile Rd to Napier Rd to 9 Mile Rd, back to Currie Rd and vice versa. | Iafrate Construction | 4/12 | Early October | Currie Road |
Currie Road (PERMIT PROJECT) | 8 Mile Road to 9 Mile Road | Lyon Township | Gas main work | Yes, residential access maintained. | 8 Mile Rd to Napier Rd to 10 Mile Rd and vice versa. | Consumers Energy | 4/14 | Mid May | Permit Work & Short-Term Road Closures |
*Grand River Avenue Bridge over CSX Railroad | Taft Road and Novi Road | Novi | Painting sections of the structure. | No, expect right (outside) lane closures. | No | Davis Construction Company | 4/5 | Early May | Grand River Avenue Bridge |
*Mann Road (PERMIT PROJECT) | Clintonville Road to Sunburst Avenue | Independence Township | Sanitary sewer installation for a private development. | Yes, business and residential access maintained. | Lake Angelus Rd to Rohr Rd, back to Mann Rd and vice versa. | Pamar Enterprises | 5/3 | 5/31 | Permits & Short-Term Road Closures |
Maple Road | Franklin Road to Inkster Road | Bloomfield Township | Resurfacing, improved drainage, new traffic signals, addition of a center left-turn lane (from Inkster to east of Norham Rd), new curb/gutter, culvert replacement east of Norham Rd and pathway construction on north side of Maple Rd. | Yes, residential and business access maintained. | Inkster Rd to Walnut Lake Rd to Franklin Rd, back to Maple Rd and vice versa. | Dan's Excavating | 4/8 | Late September | Maple Road |
Maple Road (PERMIT PROJECT) | Middlebelt Road to Orchard Lake Road | West Bloomfield Township | Consumers Energy pipeline work. | No, there are lane and road-shoulder closures. Additionally, flaggers will direct traffic when necessary. | No | Michels Corporation | 4/15 | Late August | Consumers Energy |
Middlebelt Road (PERMIT PROJECT) | 13 Mile Road to Maple Road | Farmington Hills and West Bloomfield Township | Consumers Energy pipeline work. | No, there are lane and road-shoulder closures. Additionally, flaggers will direct traffic when necessary. | No | Michels Corporation | 4/15 | Late August | Consumers Energy |
*Preservation Overlays (Simple Resurfacing) | Various heavier traveled roads throughout Oakland County | Various | Simple resurfacing with placing 2-2.5 inches of asphalt on the road surface; work is weather-dependent. | No, expect traffic delays. | No | Cadillac Asphalt and Ace-Saginaw Paving | May, TBA | TBA | 2021 Project List |
Sashabaw Road/Oakhill Road Roundabout | Sashabaw Road and Oakhill Road intersection | Brandon and Independence townships | Construction of a compact roundabout, reconstruction one-third mile of roadway with asphalt, improved drainage, Americans with Disabilities Act-compliant crosswalks, lighting and new curbs and gutters. | Yes | Sashabaw Rd detour: Seymour Lake Rd to Baldwin Rd to Clarkston Rd, back to Sashabaw. Oakhill Rd detour: Perry Lake Rd to Seymour Lake Rd to Dartmouth Rd back to Oakhill Rd | TBA | Summer of 2021 | Fall, TBA | Oakhill/Sashabaw Road Compact Roundabout |
Spot Resurfacing | Various heavier traveled roads throughout Oakland County | Various | Milling (grinding of pavement) on smaller sections of roads and paving with asphalt. Work is weather-dependent. | No, expect traffic delays. | No | TBA | TBA | TBA | 2021 Project List |
Subdivision Roads (Special Assessment District) | Various subdivision roads in Oakland County townships | Various townships | Reconstruction and resurfacing roads with asphalt. | No | No | Various | Various start dates | Late fall | Special Assessment District (SAD) Projects |
Tindall Road (PERMIT PROJECT)
| North of East Holly Road
| Groveland and Springfield townships
| Underground tunnel construction for a private business.
| No
| No
| Burroughs Material
| 3/1
| COMPLETE | Permit Work & Short-Term Road Closures |
*Walton Blvd. | Dixie Hwy to east of Sashabaw Road | Waterford Township | Reconstruction of road including asphalt paving, upgrading traffic signal, Americans with Disabilities Act-compliant crosswalks and new curb. | Yes, Walton Blvd. from Dixie Hwy to Floradale Rd is closed until approximately 5/3. | Dixie Hwy to Sashabaw Rd, back to Walton Blvd and vice versa. | Pro-Line Asphalt Paving | 4/19 | Early fall | Walton Blvd. |