Posted on: September 4, 2020

[ARCHIVED] PROJECTS THAT COULD DELAY TRAFFIC ON RCOC ROADS SEPT. 4 - SEPT. 11 OR MIGHT START SHORTLY THEREAFTER

Road construction update image

The following projects may cause traffic delays on Road Commission for Oakland County (RCOC) roads between Sept. 4 and Sept. 11 or may start shortly thereafter. 

It is RCOC’s goal to conduct road improvement projects in a way that interferes with traffic as little as possible. This list includes both Road Commission projects and projects conducted by others, under permit, on roads under the jurisdiction of the Road Commission.

Please note: This information is subject to change. Projects can change from day to day, and traffic delays can develop in a matter of minutes due to weather, emergency situations, etc.

The project list is attached.                                        

Additional information about current and upcoming projects can also be viewed on the RCOC website:   2020 RCOC ROAD CONSTRUCTION PROJECTS (http://www.rcocweb.org/189/Road-Projects).

2020 RCOC Road Construction and Permit Projects (9/4/20 update)

Road

Project Limits

Community or Communities

Project Description

Closure

Detour

Prime Contractor

Start Date

Anticipated Completion

Project Information

12 Mile Road (Greenfield Road to Coolidge Road)

From Greenfield Road to Coolidge Road

Berkley

Resurfacing project, improvements to side street approaches, drainage, install Americans with Disabilities Act-compliant crosswalks, new signage and pavement markings.

No, two-way traffic maintained

No

Pro-Line Asphalt Paving

6/1

Mid to late October

12 Mile Road (Greenfield to Coolidge)

12 Mile Road (Lahser Road to Telegraph Road)

From Lahser Road to Telegraph Road

Southfield

Resurfacing project that includes paving with asphalt, some new curbs/gutters, Americans with Disabilities Act-compliant crosswalks/ramps, new pedestrian signals and guardrail improvements.

No

No

Cadillac Asphalt

6/1

SUBSTANTIALLY COMPLETE

12 Mile Road (Lahser to Telegraph)

12 Mile Road (SIGNAL MODERNIZATION PROJECT 2019-2020)

From east of Woodward Avenue (M-1) to west of Connecticut Avenue (west of Campbell Road)

Royal Oak

Upgrades to traffic signals, pedestrian crosswalks/sidewalks and improved street lighting. Project includes 10 locations.

No; however, expect lane closures

No

Dan’s Excavating

10/28/19 (underground infrastructure work)

September, TBA

12 Mile Signal Modernization Project

Baldwin Road (Phase II)

From Gregory Road to Waldon Road

Orion Township

Reconstruction and widening of Baldwin Road including: 3 roundabouts (Great Lakes Athletic Center, Maybee and Waldon roads), drainage, Americans with Disabilities Act-compliant crosswalks, improved lighting, pedestrian paths, concrete curbs and gutters.


No, expect lane closures.

No

Dan’s Excavating

3/30/20

Late fall of 2020 (behind the curb restoration and landscaping to continue in 2021)

Baldwin Road (Orion Township)

Chubb Road (PERMIT PROJECT)

From 9 Mile Road to 10 Mile Road

Lyon Township

Gravel road paving between 10 Mile Road and Hidden River Drive.

Yes; however, residential access will be maintained

9 Mile Rd to Napier Rd to 10 Mile Rd, back to Chubb Rd and vice versa

Lyon Township

6/1

Late September

Traffic Alert

Concrete Slab Replacement

Various heavier-traveled roads throughout Oakland County

Various

Remove and replace concrete

No; however, expect lane closures

No

Cipparrone Contracting

6/15

TBA

Concrete Slab Replacement

Cooley Lake Road (CULVERT REPLACEMENT)

West of Ford Road from Teeple Creek Lane to just west of Forest Edge Drive

Commerce and White Lake townships

Remove and replace a culvert under the road.

Yes

South Duck Lake Rd to Commerce Rd to Carey Rd, back to Cooley Lake Rd

DiPonio Contracting

8/5

Late September

Cooley Lake Road Culvert Replacement

Davisburg Road (CULVERT REPLACEMENT)

Just east of Oakhurst Road

Springfield Township

Culvert removal and replacement.

Yes

Milford Rd to White Lake Rd to Ormond Rd, back to Davisburg Rd and vice versa.

Aielli Construction

7/31/20

Fall, TBA

Davisburg Road Culvert Replacement

Dequindre Road

From Utica Road to Collins Avenue

Rochester Hills/Shelby Township border

Reconstruction, widening to 5 lanes including a continuous center left-turn lane, right-turn lanes at major intersections, new concrete curbs/gutters and storm sewers, traffic signal upgrades and Americans with Disabilities Act-compliant crosswalks.




Yes, the east leg of Auburn Rd at Dequindre Rd closure is Aug. 12-early Sept.

Yes, the east leg of Auburn Rd at Dequindre detour beginning Aug. 12-early Sept. is: Dequindre Rd to Hamlin Rd to Ryan Rd, back to Auburn Rd and vice versa.




Dan’s Excavating

5/18

Late fall

Dequindre Road

Elizabeth Lake Road (PERMIT PROJECT)

From M-59 to Cass Lake Road

Waterford Township

Sanitary sewer and water main repairs.

Yes; however, home and business access within the construction zone is maintained.

M-59 to North Cass Lake Rd, back to Elizabeth Lake Rd and vice versa.

Oakland County Office of the Water Resources Commissioner

6/10

Fall, TBA

Permit Work and Short-Term Road Closures

Fish Lake Road

From Fenton Road to Elliott Road

Holly and Rose townships

Resurfacing, guardrail replacement and new lane markings.

No

No

Cadillac Asphalt

10/5 (will take place once railroad crossing repairs on Fish Lake Road south of Grange Hall Road are complete)

11/6

Federal Aid Resurfacing

Fish Lake Road (PERMIT PROJECT)

From Grange Hall Road to Fenton Road (work is between Victoria Lane and Whistle Stop Lane)

Holly Township

Railroad track crossing repairs done in advance of resurfacing work on Fish Lake Road from Elliott Road to Fenton Road.

Yes; however, residential and business access will be maintained.

Academy Rd to Oakland St to Saginaw Rd to Grange Hall Rd, back to Fish Lake Rd and vice versa

Canadian National

9/21 (railroad track crossing repairs)

10/5 (approximate)

Permit Work and Short-Term Road Closures

Grand River Avenue Bridge over CSX Railroad

Between Novi Road and Taft Road

City of Novi

Bridge rehabilitation work including replacement of barrier walls, sidewalk replacement, new pedestrian rails along bridge and guardrail.

No, one lane of traffic maintained in each direction. Pedestrian access maintained opposite side of bridge work.






No

Davis Construction Company

6/8

Mid-November

Grand River Avenue Bridge

Grass Lake Road

From Ormond Road to Steeple Hill Road

White Lake Township

Gravel road paving with asphalt, improved drainage, some realignment of road and new guardrail installation.

Yes; however, residential access will be maintained

Ormond Road to M-59 (Highland Road) to Hill Road, back to Grass Lake Road and vice versa. Additional closure information:      CLICK HERE

Dan’s Excavating

5/4

Late fall

Grass Lake Road

*Holly Road

From north of Grange Hall Road north to the county border

Holly Township and Village of Holly

4.5 miles of asphalt resurfacing, reconstruction of road in three areas to improve drainage, reconstruction of the retaining wall/hill adjustment north of the Belford Road intersection, safety improvements on curves, new guardrail and culvert maintenance.

Yes, access to businesses, cemetery and homes maintained. Phase 1 closure is Holly Rd from Grange Hall Rd to Belford Rd (from June 23 until approximately mid-September)

Holly Road to Grange Hall Road to Dixie Hwy to Baldwin Road (Genesee County), back to Holly Road and vice versa.

Ajax

6/23

Late Fall

Holly Road

Independence Township Road Resurfacing Projects (funded by a millage)

Various heavier traveled/primary roads in Independence Township

Independence Township

Resurfacing of various roads (Andersonville, Sashabaw, Waldon and Clintonville roads this year).

Mostly open to traffic with flag control in work zones.

For more information on closures:            CLICK HERE

Cadillac Asphalt

5/8

October, TBA

Independence Township Road Improvements

Clintonville Road (part of the Independence Township road funding millage)

From Maybee Road to Waldon Road

Independence Township

Road resurfacing project – road will be closed to through traffic during work.

Yes; however, residential and business access will be maintained.

Maybee Rd to Sashabaw Rd to Clarkston Rd, back to Clintonville Rd and vice versa.



Cadillac Asphalt

8/26

Early October

Independence Township Road Improvements

Joslyn Road

From Brown Road to Pacific Drive (just south of I-75)

Auburn Hills

Remove and replace concrete slabs

No, expect left lane closures on NB and SB Joslyn Rd

No

Cipparrone Contracting

9/1

Fall, TBA

Concrete Slab Replacement

Opdyke Road (PERMIT PROJECT)

Auburn Road to University Drive

Auburn Hills and Pontiac

Widening and resurfacing work related to a new Amazon business development.

No, expect lane closures.

No

Angelo Iafrate

6/8

September, TBA

Permit Work and Short-Term Road Closures

Ormond Road

From Davisburg Road to north of White Lake Road

Springfield Township

Resurfacing, new guardrail and pavement markings.

No

No

Cadillac Asphalt

9/1

Early October

Federal Aid Resurfacing

*Pickering Road Culvert Replacements

Pickering Road (3 locations)

Bloomfield Township

Remove and replace three culverts; erosion control; asphalt paving over new culverts; water, gas and sanitary sewer relocation.

Yes, Fairhill Rd will close at Pickering Rd from July 24 through late September

Detour for Fairhill Rd traffic: Pickering Rd to Kingswood Dr, back to Fairhill Rd and vice versa

VIL Construction

March (tree removal), May-June (utility relocation) and July (culvert work)

Late fall

Pickering Road Culvert Replacements

Preservation Overlays

Various heavier-traveled roads throughout Oakland County

Various

Simple resurfacing with placing 2-2.5 inches of asphalt on the road surface; work is weather-dependent

No

No

Cadillac Asphalt

4/28/20

TBA

Preservation Overlays

Quick Road (PERMIT PROJECT)

From North Holly Road to Fish Lake Road

Holly Township

Consumers Energy pipeline replacement

Yes, residential access maintained.

EB traffic detour is Fish Lake Rd to Elliott Rd to North Holly Rd (open to SB traffic only), back to Quick Rd. WB detour is North Holly Rd to Grange Hall Rd to Fish Lake Rd, back to Quick Rd.


Consumers Energy

9/1

9/4

Consumers Energy Saginaw Trail Pipeline

Sashabaw Road (CULVERT REPLACEMENT)

Whipple Lake Canal, just south of the Sashabaw Road/Pine Knob Road intersection

Independence Township

Remove and replace a culvert under the road.

Yes

Clarkston Rd to Baldwin Rd to Seymour Lake Rd, back to Sashabaw Rd and vice versa

Dan’s Excavating

8/11

Early November

Sashabaw Road Culvert Replacement

Spot Resurfacing

Various heavier-traveled roads throughout Oakland County

Various

Milling (grinding of pavement) on smaller sections of roads and paving with asphalt. Work is weather-dependent.

No

No

Florence Cement, Pro Line Asphalt and Cadillac Asphalt

4/20/20

TBA

Spot Resurfacing

Subdivision Roads (special assessment districts)

Various subdivision roads in Oakland County townships

Various townships

Reconstruction and resurfacing road with asphalt.

No

No

Various

Various

Late Fall

Special Assessment District (SAD) Projects

Wise Road (CULVERT REPLACEMENT)

Over the Huron River located between Carroll Lake Road and Union Lake Road

Commerce Township

Remove and replace culvert under the road.

Yes

Union Lake Rd to Commerce Rd to Carroll Lake Rd, back to Wise Rd and vice versa

Blaze Contracting

7/6

Mid-September

Wise Road Culvert Replacement

*indicates updated project; TBA (To Be Announced)