[ARCHIVED] PROJECTS THAT COULD DELAY TRAFFIC ON RCOC ROADS OCT. 16 AND OCT. 23 OR MIGHT START SHORTLY THEREAFTE

construction update image

The following projects may cause traffic delays on Road Commission for Oakland County (RCOC) roads between Oct. 16 and Oct. 23 or may start shortly thereafter. 

It is RCOC’s goal to conduct road improvement projects in a way that interferes with traffic as little as possible. This list includes both Road Commission projects and projects conducted by others, under permit, on roads under the jurisdiction of the Road Commission.

Please note: This information is subject to change. Projects can change from day to day, and traffic delays can develop in a matter of minutes due to weather, emergency situations, etc.

The project list is attached.                                         

Additional information about current and upcoming projects can also be viewed on the RCOC website:   2020 RCOC ROAD CONSTRUCTION PROJECTS (http://www.rcocweb.org/189/Road-Projects).

2020 RCOC Road Construction and Permit Projects  (10/16/19 update)

Road

Project Limits

Community or Communities

Project Description

Closure

Detour

Prime Contractor

Start Date

Anticipated Completion

Project Information

*12 Mile Road (Greenfield Road to Coolidge Hwy)

From Greenfield Road to Coolidge Hwy.

Berkley

Resurfacing project, improvements to side street approaches, drainage, install Americans with Disabilities Act-compliant crosswalks, new signage and pavement markings.

No, two-way traffic maintained

No

Pro-Line Asphalt Paving

6/1

Late October 

12 Mile Road (Greenfield to Coolidge)

12 Mile Road (SIGNAL MODERNIZATION PROJECT 2019-2020)

From east of Woodward Avenue (M-1) to west of Connecticut Avenue (west of Campbell Road)

Royal Oak

Upgrades to traffic signals, pedestrian crosswalks/sidewalks and improved street lighting. Project includes 10 locations.

No; however, expect lane closures

No

Dan's Excavating

10/28/19 (underground infrastructure work)

Late October

12 Mile Signal Modernization Project

Baldwin Road (Phase II)

From Gregory Road to Waldon Road

Orion Township

Reconstruction and widening of Baldwin Road including: 3 roundabouts (Great Lakes Athletic Center, Maybee and Waldon roads), drainage, Americans with Disabilities Act-compliant crosswalks, improved lighting, pedestrian paths, concrete curbs and gutters.

No, expect lane closures.

No

Dan's Excavating

3/30

Late fall of 2020 (behind the curb restoration and landscaping to continue in 2021)

Baldwin Road (Orion Township)

Concrete Slab Replacement

Various heavier-traveled roads throughout Oakland County

 

 

 

 

Various

Remove and replace concrete

No; however, expect lane closures

No

Cipparrone Contracting

6/15

Late fall

Concrete Slab Replacement

Cooley Lake Road (CULVERT REPLACEMENT)

West of Ford Road from Teeple Creek Lane to just west of Forest Edge Drive

Commerce and White Lake townships

Remove and replace a culvert under the road.

No

No

DiPonio Contracting

8/5

EXPECTED TO OPEN TODAY (10/16)

Cooley Lake Road Culvert Replacement

Davisburg Road (CULVERT REPLACEMENT)

Just east of Oakhurst Road

Springfield Township

Culvert removal and replacement.

Yes

Milford Rd to White Lake Rd to Ormond Rd, back to Davisburg Rd and vice versa.

Aielli Construction

7/31

Late October

Davisburg Road Culvert Replacement

*Dequindre Road

From Utica Road to Collins Avenue

Rochester Hills/Shelby Township border

Reconstruction, widening to 5 lanes including a continuous center left-turn lane, right-turn lanes at major intersections, new concrete curbs/gutters and storm sewers, traffic signal upgrades and Americans with Disabilities Act-compliant crosswalks.

Yes, the west side of Auburn Rd at Dequindre Rd is closed through approximately Oct. 20. Additionally, Dequindre north of Auburn Rd to Collins Ave. expected to close to through traffic Oct. 20 through early November.

Yes. For detour information for the west side of Auburn Rd closure at Dequindre Rd AND the closure of Dequindre Rd from Auburn Rd to Collins Ave., visit:          CLICK HERE

Dan's Excavating

5/18

Late fall

Dequindre Road

Elizabeth Lake Road (PERMIT PROJECT)

From M-59 to Cass Lake Road

Waterford Township

Sanitary sewer and water main repairs.

Yes, however, business access within the construction zone is maintained.

M-59 to North Cass Lake Rd, back to Elizabeth Lake Rd and vice versa.

Oakland County Office of the Water Resources Commissioner

6/10

November, TBA

Permit Work and Short-Term Road Closures

Fish Lake Road

From Fenton Road to Elliott Road

 

 

Holly and Rose townships

Resurfacing, guardrail replacement and new lane markings.

No

No

Cadillac Asphalt

10/12

Early November

Federal Aid Resurfacing

Grand River Avenue Bridge over CSX Railroad

Between Novi Road and Taft Road

City of Novi

Bridge rehabilitation work including replacement of barrier walls, sidewalk replacement, new pedestrian rails along bridge and guardrail.

No, one lane of traffic maintained in each direction. Pedestrian access maintained opposite side of bridge work.

No

Davis Construction Company

6/8

Mid-November

Grand River Avenue Bridge

Haggerty Road (PERMIT PROJECT)

North of 8 Mile Road (near Orchard Hill Place)

Novi

Buckeye pipeline repair work

No. Haggerty Road will be reduced to one lane in each direction just north of 8 Mile Road.

No

Buckeye Pipeline

9/9

Late October

Permit Work & Short-Term Road Closures

Holly Road

From north of Grange Hall Road north to the county border

Holly Township and Village of Holly

4.5 miles of asphalt resurfacing, reconstruction of road in three areas to improve drainage, reconstruction of the retaining wall/hill adjustment north of the Belford Road intersection, safety improvements on curves, new guardrail and culvert maintenance.

No

No

Ajax

6/23

COMPLETE

Holly Road

*Nine Mile Road (PERMIT PROJECT)

Nine Mile Road just north of Grand River Avenue

Farmington

Water main repairs

Yes

Grand River Ave to Middlebelt Rd, back to Nine Mile Rd and vice versa

City of Farmington

10/15

11/2

City of Farmington

*Pickering Road Culvert Replacements

Pickering Road (3 locations)

Bloomfield Township

Remove and replace three culverts; erosion control; asphalt paving over new culverts; water, gas and sanitary sewer relocation.

Yes, Fairhill Rd will close at Pickering Rd from July 24 through late September

Detour for Fairhill Rd traffic: Pickering Rd to Kingswood Dr, back to Fairhill Rd and vice versa

 

 

VIL Construction

May-June (utility relocation) and July (culvert work)

Late October

Pickering Road Culvert Replacements

Preservation Overlays

Various heavier-traveled roads throughout Oakland County

Various

Simple resurfacing with placing 2-2.5 inches of asphalt on the road surface; work is weather-dependent

No

No

Cadillac Asphalt

4/28

TBA

Preservation Overlays

Sashabaw Road (CULVERT REPLACEMENT)

Whipple Lake Canal, just south of the Sashabaw Road/Pine Knob Road intersection

Independence Township

Remove and replace a culvert under the road.

Yes

Clarkston Rd to Baldwin Rd to Seymour Lake Rd, back to Sashabaw Rd and vice versa

Dan's Excavating

8/11

Late October

Sashabaw Road Culvert Replacement

South Blvd (PERMIT PROJECT)

Between Adams Road and Donegal Drive

Rochester Hills and Troy

Water main repairs

Yes

Adams Rd to Square Lake Rd to Coolidge Hwy, back to South Blvd and vice versa

Great Lake Water Authority (Ric-Man Contracting)

10/19

11/2

Permit Work and Short-Term Road Closures

Spot Resurfacing

Various heavier-traveled roads throughout Oakland County

Various

Milling (grinding of pavement) on smaller sections of roads and paving with asphalt. Work is weather-dependent.

No

No

Florence Cement, Pro Line Asphalt and Cadillac Asphalt

4/20

TBA

Spot Resurfacing

Subdivision Roads (special assessment districts)

Various subdivision roads in Oakland County townships

Various townships

Reconstruction and resurfacing road with asphalt.

No

No

Various

Various

Late Fall

Special Assessment District (SAD) Projects

Welch Road (PERMIT PROJECT)

Welch Road just north of 14 Mile Road

Commerce Township

Water main replacement

Yes

14 Mile Rd to Decker Rd to Maple Rd, back to Welch Rd and vice versa

Great Lakes Water Authority (Major Cement Company)

TBA

TBA

Permit Work and Short-Term Road Closures

 *indicates new or updated project; TBA (To Be Announced)

Road Construction & Permit Projects
Facebook Twitter Email

Other News in Press Releases