11 Mile Road Culvert Replacement
| Just east of South Hill Road
| Lyon Township
| Culvert removal and replacement.
| No. Flaggers will direct traffic during the work.
| No
| Fonson Company, Inc.
| 10/4
| SUBSTANTIALLY COMPLETE OPEN TO TRAFFIC | 11 Mile Culvert Replacement |
12 Mile Road | Lahser Road to Evergreen Road | Southfield | Reconstruction of road including asphalt paving, traffic signal upgrades, adding right-turn lanes at several locations, Americans with Disabilities Act-compliant crosswalks, pathway construction and new curbs and gutters. | No. Two-way traffic maintained. | No | M.L. Chartier Excavating, Inc. | 5/24 | Late November | 12 Mile Road, Lahser to Evergreen |
14 Mile Road (PERMIT PROJECT)
| Eastbound 14 Mile Road from Rochester to Campbell Road
| Royal Oak and Clawson
| City of Royal Oak water main replacement.
| No. Expect eastbound right (outside) lane closure for the work.
| No
| City of Royal Oak
| 8/30
| SUBSTANTIALLY COMPLETE (behind the curb restoration will continue with a periodic lane closure) | Permit Work & Short-Term Road Closures |
14 Mile Road (PERMIT PROJECT) | Decker/Novi Road to Walled Lake Road | Commerce Township, Novi and Walled Lake | Great Lakes Water Authority watermain replacement. | Yes. | Decker Rd to Maple Rd to East Walled Lake Dr, back to 14 Mile Rd and vice versa. | Great Lakes Water Authority | 1/4 | Late December | Permit Work & Short-Term Road Closures |
Avon Road | John R Road to 23 Mile Road; including the Avon/Dequindre Road intersection | Rochester Hills and Shelby Township | Bridge removal and replacement. Project also includes the construction of a roundabout at the Dequindre/Avon Road intersection (expected to start summer of 2022). | Yes; residential, park and business access maintained. | John R Rd to Hamlin Rd to Ryan Rd to 23 Mile Rd, back to Avon/Dequindre Rd. | Z Contractors | 11/1 | August of 2022 (bridge and roundabout at Avon/Dequindre Road to reopen to traffic) | Avon Road, Dequindre to 23 Mile Road |
Big Beaver Road (PERMIT PROJECT) | Just west of Dequindre Road (westbound lanes) | Troy | City of Troy watermain and sanitary sewer work. | No. Westbound Big Beaver Road will have lane closures just west of Dequindre Road (one lane will remain open for traffic during the work). | No | Pamar Enterprises | 4/19 | November, TBA | City of Troy Construction Updates |
Brown Road | West of Giddings Road to M-24 (Lapeer Road) | Orion Township | Concrete repairs | No, expect lane closures | No | Cipparrone Contracting | 10/18 | Late November | Concrete Replacement |
Dequindre Road (part of the Avon Road project) | Dequindre Road from Hamlin Road to 23 Mile Road | Rochester Hills | Closure for the Avon Road bridge demolition and construction of a roundabout at the Dequindre Road/Avon Road intersection. | Yes, access to businesses and residential properties maintained. | Hamlin Rd to Ryan Rd to 23 Mile Rd, back to Dequindre Rd and vice versa. | Z Contractors | 11/1 | August of 2022 | Dequindre Road (part of the Avon Road construction project) |
*Kent Lake Road (PERMIT PROJECT) | Grand River Avenue to Silver Lake Road | Lyon Township | Watermain installation. | Yes, the road will fully close just north of the Kent Lake Elementary School. | Grand River Ave to New Hudson Dr to Pontiac Trl to Silver Lake Rd, back to Kent Lake Rd and vice versa | Stante Excavating | 11/13 | 11/13 (evening) | Permit Work & Short-Term Road Closures |
Maybee Road | Dixie Highway to Sashabaw Road (culvert is located just west of Waterford Road) | Independence Township | Culvert removal and replacement | Yes, access to business and residential property maintained | Sashabaw Rd to Waldon Rd to M-15 to Dixie Hwy, back to Maybee Rd and vice versa. | Superior Company, Inc. | 11/10 | 11/12 (evening) | Permit Work & Short-Term Road Closures |
*Milford Road Culvert Replacement | Just east of Water Road over Buckhorn Creek | Rose Township | Remove and replace a culvert under the road. Work also includes asphalt paving, new storm sewers, replacement of guardrails and installation of curbs and gutters. | Yes. | Fenton Rd to Hickory Ridge Rd to Middle Rd, back to Milford Rd and vice versa. | Superior Company, Inc. | 9/15 | 11/19 (weather-dependent) | Milford Road Culvert |
Orchard Lake Road (northbound) | Long Lake Road to Indian Trail | West Bloomfield Township | Guardrail replacement | Yes, just northbound Orchard Lake Rd. Expect periodic closures from 8:30 am to 4:30 pm. Southbound Orchard Lake Rd will remain open to traffic. | For northbound Orchard Lake Rd traffic detour is Long Lake Rd to Middlebelt Rd, back to Orchard Lake Rd. | RCOC | 7/8 | TBA | Permit Work & Short-Term Road Closures |
Preservation Overlays (Simple Resurfacing) | Various heavier traveled roads throughout Oakland County | Various | Simple resurfacing with placing 2-2.5 inches of asphalt on the road surface; work is weather-dependent. | No, expect traffic delays. | No | Cadillac Asphalt and Ace-Saginaw Paving | 5/11 | Mid-November | 2021 Project List |
Sashabaw Road and Oakhill Road Roundabout
| Sashabaw Road and Oakhill Road intersection
| Brandon and Independence townships
| Construction of a compact roundabout, reconstruction of one-third mile of roadway with asphalt, improved drainage, Americans with Disabilities Act-compliant crosswalks, lighting and new curbs and gutters.
| No
| No
| Iafrate Construction
| 9/7
| COMPLETE | Oakhill/Sashabaw Road Compact Roundabout |
Subdivision Roads (Special Assessment District) | Various subdivision roads in Oakland County townships | Various townships | Reconstruction and resurfacing roads with asphalt. | No | No | Various | Various start dates | Late fall | Special Assessment District (SAD) Projects |