14 Mile Road (PERMIT PROJECT) | Eastbound 14 Mile Road, just east of I-75 from Concord Street to John R Road | Madison Heights and Troy | Consumers Energy gas main relocation. | EB 14 Mile Rd is closed between Concord St. and John R Rd. WB 14 Mile Rd remains open to traffic. Business access maintained off of Mandoline Ave. The EB 14 Mile crossover to Elliott St/Oakland Mall remains accessible. | EB 14 Mile Rd detour is Stephenson Hwy to 12 Mile Rd to John R Rd, back to 14 Mile Rd. | Consumers Energy | 11/17 | Late November | Consumers Energy |
14 Mile Road (PERMIT PROJECT) | Just west of the Novi Road/Decker Road intersection. | Novi and Walled Lake | The eastbound right lane on 14 Mile Road, just west of the Novi Road/Decker Road intersection, is closed for Great Lakes Water Authority watermain work. | No; expect a lane shift in the work zone. | No. | Great Lakes Water Authority | 10/3 | Mid-November | Great Lakes Water Authority |
Bald Mountain Road (PERMIT PROJECT)
| Dutton Road to Roxbury Drive (south of Silverbell Road)
| Orion Township
| Consumers Energy high-pressure gas transmission line repairs.
| No.
| No.
| Consumers Energy
| 4/19
| COMPLETE | Consumers Energy |
Clarkston Road (PERMIT PROJECT) | Adams Road to Lake George Road | Oakland Township | Drainage improvements, storm sewer installation and gravel road paving by private developers. | Yes. Residential and business access will be maintained. | Lake George Rd to Stoney Creek Rd to Adams Rd, back to Clarkston Rd and vice versa. | Ajax Paving | 8/4 | Late November (the road will close again in the spring of 2023 for paving) | Permit Work & Short-Term Road Closures |
*East Glass Road (PERMIT PROJECT) | Ortonville Road (M-15) and Viola Drive | Brandon Township | Storm sewer removal and installation work done by the Oakland County Water Resources Commissioner's Office. | Yes, residential access will be maintained. | Granger Rd to South Hadley Rd to Seymour Lake Rd to Ortonville Rd (M-15), back to East Glass Rd and vice versa. | Zito Construction, on behalf of the Oakland County Water Resources Commissioner's Office. | 8/29 | Mid to late November (project completion originally expected on 12/31). | Permit Work & Short-Term Road Closures |
Hatchery Road | Dixie Highway to Airport Road (the work is just west of Frembes Road) | Waterford Township | Bridge replacement over the Clinton River, culvert replacement west of the bridge, demolition of the wooden pedestrian bridge (new bridge will facilitate pedestrians) and new guardrails. | The road is closed over the Clinton River. Residential access is maintained east and west of the bridge. | Dixie Hwy to Williams Lake Rd to Airport Rd, back to Hatchery Rd and vice versa. | Toebe Construction | 6/13 | Mid-November | Hatchery Road Bridge Replacement over the Clinton River |
Joint Repairs | Various heavier traveled roads. | Commerce Township, Highland Township, Novi, Troy and Wixom | Milling (grinding pavement) road joints and paving with asphalt. | No. During the work, the roads will remain open with flaggers directing traffic. | No | Cadillac Asphalt | 6/16 | Fall, TBA | Joint Repairs |
Long Lake Road (PERMIT PROJECT) | North and south legs of Franklin Road (closure is between Groton Road and Pine Tree Trail) | Bloomfield Township | Bloomfield Township sanitary sewer work. | Yes, Long Lake Rd, just east of the south leg of Franklin Rd, is closed. Residential and business access maintained. | Telegraph Rd to Lone Pine Rd to Franklin Rd, back to Long Lake Rd and vice versa. Pine Tree Trl and Groton Rd residential access maintained from Franklin Rd. | Bloomfield Township | 9/19 | Late November | Bloomfield Township |
Maloney Street Bridge Replacement | North of Drahner Road over Clear Lake and Long Lake | Oxford Township | Removal and replacement of a bridge. | The waterway under the bridge is closed to boats and other recreational traffic during the project. Residential access maintained. | No, residential access is maintained via a single-lane temporary road. | F.H. Paschen | 7/5 | Late November | Maloney Street Bridge Replacement |
Orchard Lake Road | Middlebelt Road to Old Telegraph Road | Sylvan Lake, West Bloomfield Township, Bloomfield Township and Pontiac | Road resurfacing work, including asphalt paving, concrete slab replacements, Americans with Disabilities Act-compliant crosswalks, traffic signal upgrades, drainage improvements and widening east of Middlebelt Rd to accommodate a center left-turn lane. | No; one lane will remain open in each direction. | No | Florence Cement | 6/27 | Mid-November | Orchard Lake Road, Middlebelt to Old Telegraph Road |
Orchard Lake Road | 13 Mile Road to 14 Mile Road | Farmington Hills | Resurfacing /reconstruction project that includes asphalt paving, concrete replacement, roundabout construction at the Orchard Lake Plaza entrance and a four-lane boulevard from Hunters Lane to 14 Mile Rd. | Yes, northbound Orchard Lake Rd is closed. Southbound Orchard Lake Rd to remain open with business access maintained. | Northbound Orchard Lake Rd traffic detour is 13 Mile Rd to Northwestern Hwy back to Orchard Lake Rd. | M.L. Chartier | 3/21 | Early November | Orchard Lake Road, 13 Mile to 14 Mile Road |
Preservation Overlays (Simple Resurfacing) | Various heavier traveled roads throughout Oakland County | Various | Simple resurfacing with placing 2-2.5 inches of asphalt on the road surface; work is weather-dependent. | No. Expect traffic delays. | No | Cadillac Asphalt and Ace-Saginaw Paving | 4/18 | Mid-November | 2022 Project List |
Walton Blvd. | Sashabaw Road to Clintonville Road | Waterford Township | Removal of existing concrete, resurfacing with asphalt, minor drainage improvements, Americans with Disabilities Act (ADA)-compliant crosswalks, traffic signal upgrade at Mason School entrance and replacement of some curbs and gutters. | No. One lane of traffic is open in each direction during the work. | No. | Ajax Paving | 7/25 | Mid-November | Walton Blvd. |