The re-opening of Milford Road, just east of Water Road in Rose Township, has been delayed until approximately Monday, Nov. 22.
The road, which has been closed since Sept. 15 for the replacement of a culvert under the road, was originally scheduled to reopen today, November 15. The reopening was delayed primarily due to weather issues.
The culvert has been replaced. The contractor has the following work to complete:
- Asphalt paving over the new culvert (approximately 500 feet)
- Installation of new guardrail
- Striping of the new pavement
For more information on the Milford Road culvert replacement project, visit: https://www.rcocweb.org/601/Milford-Road-Culvert-Replacement.