10 Mile Road | From Evergreen Road to Greenfield Road | Southfield | Concrete slab removal and replacement, curb/gutter installation, Americans with Disabilities Act-compliant crosswalks and upgraded bus stops. Access to businesses maintained throughout the project. | No; expect lane closures. During Phase 1, left-turns will be prohibited on Southfield Road to 10 Mile Road, date TBA. | No | Mark Anthony Contracting | 7/15/19 | Late fall | 10 Mile Road Concrete Slab Replacement |
*10 Mile Road (PERMIT PROJECT) | East of Telegraph Road at Berg Road | Southfield | Sanitary sewer rehabilitation. | No, westbound right (outside) lane is closed near Berg Road; traffic shifted to the open lane | No | Oakland County Office of Water Resources Commissioner | 7/30/19 | Early November | Oakland County WRC |
12 Mile and Novi Road intersection | 12 Mile Road and Novi Road intersection (including work on Novi Road approaches to intersection) | Novi | Concrete slab replacement, Americans with Disabilities Act-compliant sidewalk ramps and upgrades to the pedestrian signals. | No | No | Mark Anthony Contracting | 6/17/19 | Substantially complete | 12 Mile/Novi Road Intersection |
*12 Mile Road (PERMIT PROJECT) | West of Telegraph at Case Avenue | Southfield | Underground utility work | No | No; however, the right (outside) eastbound lane on 10 Mile Road at Case Avenue is closed | AT&T | 5/10/19 | Late October | Traffic Alert |
Baldwin Road | From the Pontiac/Auburn Hills city limits to south of I-75 entrance ramps | Auburn Hills | Remove and replace concrete slabs | No | No; however, expect lane closures | Florence Cement | 8/26/19 | Mid-October | Concrete Slab Replacements |
Baldwin Road (Phase I) (carryover project from 2018) | From Morgan Road to Gregory Road | Orion Township | Behind the curb and driveway restoration; street lighting (DTE); Americans with Disabilities Act -compliant crosswalks/ sidewalks and new sign installation | No; however, expect lane closures | No | Dan's Excavating | 4/8/2019 | Substantially complete and open to traffic | Baldwin Road |
Baldwin Road (Phase II) | From Gregory Road to Waldon Road | Orion Township | Reconstruction of Baldwin Road including: 3 roundabouts (Great Lakes Athletic Center, Maybee and Waldon roads), drainage, widening, Americans with Disabilities Act-compliant crosswalks, improved lighting, pedestrian paths, concrete curb and gutter. | Maybee Road and the east side of Waldon Road are closed at Baldwin Road; Baldwin Road remains open to traffic | Yes, for Maybee Road and the east side of Waldon Road detours: CLICK HERE | Dan's Excavating | 6/17/19 | 2020, TBA (seasonal shutdown of work will take place in late fall of 2019 and restart in the spring of 2020) | Baldwin Road (Orion Township) |
Maybee Road at Baldwin Road (Part of the Baldwin Road Phase II construction) | Maybee Road and Baldwin Road eastbound and westbound approaches | Orion Township | Eastbound and westbound Maybee Road at Baldwin Road are closed for roundabout construction. | Yes; however, two-way traffic is maintained on Baldwin Rd | For detour routes: CLICK HERE | Dan's Excavating | 7/11/19 | Late fall | Baldwin Road |
Waldon Road at east side of Baldwin Road (Part of the Baldwin Road Phase II construction) | Waldon Road east half at Baldwin Road | Orion Township | Roundabout construction | Yes (west side of intersection at Baldwin Road will remain open to traffic) | Baldwin Rd to Clarkston Rd to Joslyn Rd, back to Waldon Rd and vice versa | Dan's Excavating | 9/23/19 | Late fall | Baldwin Road |
Central Drive | From Indianwood Road to the Village of Lake Orion limits | Orion Township | Pulverizing existing road surface, asphalt paving, some guardrail replacement and minor drainage improvements. | No | No | Asphalt Specialists Inc | 8/5/19 | Mainline paving is complete (miscellaneous work continues through late October) | Central Drive |
Concrete Slab Replacement | Various heavier traveled roads throughout Oakland County | Various | Remove and replace concrete | No; however, expect lane closures | No | Florence Cement | 5/6/19 | Late fall | Concrete Slab Replacement |
Dixboro Road | From 8 Mile Road to 9 Mile Road | Lyon Township, Green Oak Township and South Lyon | Culvert replacement, tree removal and bad soil excavation (paving in 2020). | Yes | 9 Mile Road to Pontiac Trail to 8 Mile Rd, back to Dixboro Rd and vice versa (residential and Volunteer Park access maintained) | Dan's Excavation | 10/1/19 (expected closure to through traffic on 10/14) | Early December (paving to begin in the spring of 2020) | Dixboro Road |
Dixie Hwy | From Oakhill Road to the county line | Groveland, Holly and Springfield townships | Resurfacing with additional drainage work and guardrail replacement between Tindall and Gail Drive | No | No | Ace-Saginaw Paving Company | 7/29/19 | Late October | Federally Funded Overlays |
Grange Hall Road | From Van Road to Jossman Road | Groveland Township | Resurfacing, guardrail/sign replacement and new pavement markings. | No; however, there will be lane closures in the work zone with flag control directing traffic. | No | Ace-Saginaw Paving | 9/16/19 | Mainline paving is complete; work continues on guardrail and shoulder restoration. | Federally Funded Overlays |
Haggerty Road over the Seeley Drain (between 13 Mile and 14 Mile roads) | From 13 Mile to 14 Mile Road (culvert is located between Lilly Court and MacKenzie Drive) | Farmington Hills and Novi | Remove and replace a culvert under the road that carries the Seeley Drain. | Yes | 13 Mile Rd to M-5 to 14 Mile Rd, back to Haggerty Rd and vice versa | DiPonio Contracting | 10/3/19 | Late October | Haggerty Road Culvert Replacement over the Seeley Drain |
Heights Road (PERMIT PROJECT) | US 24 (N Broadway St) to Bellevue Avenue | Village of Lake Orion and Orion Township | Water main replacement | Yes | For detour routes: CLICK HERE | Fontana Construction | 9/30/19 | Mid-November | Village of Lake Orion |
John R (southbound John R from Long Lake to Square Lake Road is closed) | Long Lake Road to Square Lake Road | Troy | Reconstruction to a 3-lane road with a continuous center left-turn lane, drainage improvements, sewer/water improvements, curb/gutter installation, asphalt path (west side) and Americans with Disabilities Act- compliant sidewalks/crossings (east side). | Yes, southbound John R is closed | Southbound John R detour is South Blvd to Dequindre Rd, to Long Lake Rd, back to John R; northbound John R remains open to traffic | Dan's Excavating | 4/29/19 | Late fall | John R |
Livernois Road | From Avon Road to north of Walton | Rochester Hills | Reconstruction of road, improved drainage, traffic-signal modernization, upgrading sidewalks to comply with Americans with Disabilities Act, new guardrail, retaining wall repairs and replacing curbs and gutters. | Yes, southbound Livernois is closed to traffic. Northbound Livernois will remain open to traffic | The detour for southbound Livernois traffic is Tienken Rd to Adams Rd to Avon Rd back to Livernois Rd | Pro-Line Asphalt | 6/21/19 | Late fall | Livernois Road |
Maple Road and Middlebelt Road | Maple Road and Middlebelt Road intersection (roundabout construction) | West Bloomfield Township | Construction of a roundabout, improved drainage, new watermain and Americans with Disabilities Act-compliant crosswalks. | Yes, intersection is closed | For detour routes: CLICK HERE | Angelo Iafrate | 9/14/19 | Late November | Maple and Middlebelt Roundabout Construction |
*Maple Road Culvert (PART OF THE MAPLE AND MIDDLEBELT ROAD ROUNDABOUT CONSTRUCTION) | From Middlebelt Road to Inkster Road (culvert is between Glenway Drive and Bloomfield Glens Road) | West Bloomfield Township | Removal and replacement of a culvert under the road that carries Rouge River Tributary | Yes, Maple Road is closed between Middlebelt and Inkster roads | Inkster Rd to 14 Mile Rd to Middlebelt Rd, back to Maple Rd and vice versa | Angelo Iafrate | 6/29/19 | Late October | Maple Road Culvert |
Middlebelt Road (PERMIT PROJECT) | From 12 Mile Road to 13 Mile Road (emergency repair is just south of Orion Court) | Farmington Hills | Emergency road repairs | TBA | TBA | Office of the Oakland County Water Resources Commissioner | TBA | TBA | Traffic Alerts |
*Milford Road | Just east of South Fenton Road and the railroad tracks | Rose Township | Culvert removal and replacement. Includes paving road, new guardrail and pavement markings | Yes, residential access will be maintained east of the culvert | Milford Rd to Clyde Rd to Hickory Ridge Rd to Fenton Rd, back to Milford Rd and vice versa | Zito Construction | 9/19/10 | Mid-November | Milord Road Culvert |
Preservation Overlays | Various heavier traveled roads throughout Oakland County | Various | Simple resurfacing, placing 2-2.5 inches of asphalt on the road surface; work is weather-dependent. | No | No | Cadillac Asphalt | 4/25/19 | Late fall | Preservation Overlays |
*Sashabaw Road | From Sherwood Road to Granger Road | Brandon Township | Pave gravel road with asphalt, improved drainage, shoulder paving in areas, curb and gutter installation in areas and storm sewer installation. | Yes; however, residential access will be maintained through the project | Sherwood Rd to Perry Lake Rd to Granger Rd, back to Sashabaw Rd and vice versa | Zito Construction | 7/1/19 | Mid-October | Sashabaw Road (Sherwood to Granger) |
Sashabaw Road (I-75 to Clarkston Road) | From I-75 to just south of Clarkston Road | Independence Township | Widening road to 5 lanes with a continuous left turn lane, resurfacing, right-turn lanes where warranted and Americans with Disabilities Act -compliant sidewalks and crosswalks. | No | No | Dan's Excavating | 4/22/18 | Late fall | Sashabaw Road (I-75 to Clarkston) |
Spot Resurfacing | Various heavier traveled roads throughout Oakland County | Various | Milling short sections of roads and resurfacing with hot mix asphalt. | No | No | Cadillac Asphalt and Pro-Line Asphalt Paving | 4/22/19 | TBA | Spot Resurfacing |
*Teggerdine Road | Just north of M-59/Highland Road | White Lake Township | Remove and replace a culvert under the road. | Yes | M-59/Highland Rd to Pontiac Lake Rd, back to Teggerdine Rd and vice versa | RCOC Hwy Maintenance | 10/12/19 | 10/13/19 (evening) | Weekend, Emergency & Short-Term Road Closures |