10 Mile Road | From Evergreen Road to Greenfield Road | Southfield | Concrete slab removal and replacement, curb/gutter installation, Americans with Disabilities Act-compliant crosswalks and upgraded bus stops. Access to businesses maintained throughout the project. | No; expect lane closures. During Phase 1, left-turns will be prohibited on Southfield Road to 10 Mile Road, date TBA. | No | Mark Anthony Contracting | 7/15/19 | Late Fall | 10 Mile Road Concrete Slab Replacement |
10 Mile Road (PERMIT PROJECT) | East of Telegraph Road at Berg Road | Southfield | Sanitary sewer rehabilitation | No, westbound right (outside) lane is closed near Berg Road; traffic shifted to the open lane | No | Oakland County Office of Water Resources Commissioner | 7/30/19 | Late August | Oakland County WRC |
12 Mile and Novi Road intersection | 12 Mile Road and Novi Road intersection (including work on Novi Road approaches to intersection) | Novi | Concrete slab replacement, Americans with Disabilities Act-compliant sidewalk ramps and upgrades to the pedestrian signals | Northbound and southbound Novi Rd is closed at 12 Mile Rd; one lane in each direction will remain open on 12 Mile Rd. | Yes, for Novi Rd traffic the detour is Grand River Avenue to Meadowbrook Road to 13 Mile Rd, back to Novi Road and vice versa | Mark Anthony Contracting | 6/17/19 | Mid-September | 12 Mile/Novi Road Intersection |
12 Mile Road (PERMIT PROJECT) | West of Telegraph at Case Avenue | Southfield | Underground utility work | No | No; however, the right (outside) eastbound lane on 10 Mile Road at Case Avenue is closed | AT&T | 5/10/19 | Late August | Traffic Alert |
8 Mile Road bridge over the Rogue River
| Between Middlebelt Road and Grand River Avenue
| Farmington Hills and Livonia
| Preventative bridge maintenance including approach repairs, epoxy overlay on bridge deck and asphalt paving
| No, expect lane closures
| No
| Florence Cement
| 6/17/19
| COMPLETE | 8 Mile Bridge over the Rouge River |
Adams Road and Gunn Road | Adams Road and Gunn Road intersection (roundabout construction) | Oakland Township | Construction of a roundabout, drainage improvements, curb/gutter installation, High-Intensity Activated Crosswalk (HAWK) pedestrian crossing beacons installed at crosswalks on the north leg of the roundabout | Yes, intersection is closed to traffic | For detour routes: CLICK HERE | M.L. Chartier | 6/17/18 | Late August | Adams and Gunn Road Roundabout |
Adams Road bridges (work to be done during the Adams/Gunn roundabout construction)
| North of Gunn Road to Orion Road | Oakland Township | Preventative maintenance including bridge approach improvements, epoxy overlay on bridge deck, paving with hot mix asphalt and new guardrail | Yes; however, residential traffic will be maintained | Orion Rd to Silverbell Rd, back to Adams Rd and vice versa | Florence Cement | 6/17/19 | Late August | Adams Road Bridges |
Baldwin Road (Phase I) (carryover project from 2018) | From Morgan Road to Gregory Road | Orion Township | Behind the curb and driveway restoration; street lighting (DTE); Americans with Disabilities Act -compliant crosswalks/ sidewalks and new sign installation
| No; however, expect lane closures | No | Dan's Excavating | 4/8/2019 | Substantially complete and open to traffic | Baldwin Road |
Baldwin Road (Phase II) | From Gregory Road to Waldon Road | Orion Township | Reconstruction of Baldwin Road including: 3 roundabouts (Great Lakes Athletic Center, Maybee and Waldon roads), drainage, widening, Americans with Disabilities Act-compliant crosswalks, improved lighting, pedestrian paths, concrete curb and gutter. | Maybee Road is closed at Baldwin Road; Baldwin Road remains open to traffic | Yes, for Maybee Road detours: CLICK HERE | Dan's Excavating | 6/17/19 | 2020, TBA (seasonal shutdown of work will take place in late fall of 2019 and restart in the spring of 2020) | Baldwin Road (Orion Township) |
Maybee Road at Baldwin Road (Part of the Baldwin Road Phase II construction) | Maybee Road and Baldwin Road eastbound and westbound approaches | Orion Township | Eastbound and westbound Maybee Road at Baldwin Road are closed for roundabout construction | Yes; however, two-way traffic is maintained on Baldwin Rd | For detour routes: CLICK HERE | Dan's Excavating | 7/11/19 | Late Fall | Baldwin Road |
Carroll Lake/Cooley Lake Road intersection | Carroll Lake Road and Cooley Lake Road intersection | Commerce Township and White Lake Township border | Construction of a mini roundabout | Yes, intersection is closed | For detour routes: CLICK HERE | Commerce Construction and Landscaping Inc | 7/15/19 | 9/6/19 | Carroll Lake/Cooley Lake Road Roundabout |
Central Drive | From Indianwood Road to the Village of Lake Orion limits | Orion Township | Pulverizing existing road surface, asphalt paving, some guardrail replacement and minor drainage improvements | No | No | Asphalt Specialists Inc | 8/5/19 | Mid-September mainline paving completion | Central Drive |
Concrete Slab Replacement | Various heavier traveled roads throughout Oakland County | Various | Remove and replace concrete | No; however, expect lane closures | No | Florence Cement | 5/6/19 | TBA | Concrete Slab Replacement |
Dixie Hwy | From Oakhill Road to the county line | Groveland, Holly and Springfield townships | Resurfacing with additional drainage work and guardrail replacement between Tindall and Gail Drive | No | No | Ace-Saginaw Paving Company | 7/29/19 | Mid- September | Federally Funded Overlays |
*Dixie Hwy | Northbound Dixie Hwy entrance ramp to northbound I-75 | Holly Township and Genesee County border | Resurfacing project | No; however, the northbound Dixie Hwy entrance ramp to northbound I-75 to close for paving for approximately 2 hours on 8/12/19 | No | Saginaw-Ace Paving Company | 8/12/19 @ 1 pm | 8/12/19 @ 4 pm | Dixie Hwy |
Grand River Avenue at South Hill Road (carryover project from 2018) | Grand River Avenue and South Hill intersection | Lyon Township | Traffic signal installation is expected over the summer. Behind the curb restoration is complete | No | No | Fonson Company, Inc | 4/22/18 | Late August (new traffic signal will be fully functional) | Grand River Avenue at South Hill |
Haggerty Road and 14 Mile Road intersection (PERMIT PROJECT) | Haggerty Road and 14 Mile Road intersection | Novi, Farmington Hills, West Bloomfield Township and Commerce Township border | Adding a right-turn lane from SB Haggerty Rd to WB 14 Mile Rd and upgrades to sidewalks and pedestrian crosswalks to comply with the Americans with Disabilities Act | No; however, left-turns are prohibited from NB and SB Haggerty Rd to 14 Mile Rd. SB Haggerty traffic is shifted to the left-turn lane. | No | City of Novi | 7/18/19 | Late August | Traffic Alert |
Haggerty Road over the Seeley Drain | From 13 Mile to 14 Mile Road (culvert is located between Lilly Court and MacKenzie Drive) | Farmington Hills and Novi | Remove and replace a culvert under the road that carries the Seeley Drain | Yes | 13 Mile Rd to M-5 to 14 Mile Rd, back to Haggerty Rd and vice versa | DiPonio Contracting | 9/3/19 (tentatively) | Late September (tentatively) | Haggerty Road Culvert Replacement over the Seeley Drain |
Heights Road (PERMIT PROJECT) | US 24 (N Broadway St) to Bellevue Avenue | Village of Lake Orion and Orion Township | Water main replacement | Yes | For detour routes: CLICK HERE | Fontana Construction | TBA | TBA | Village of Lake Orion |
John R (southbound John R from Long Lake to Square Lake Road is closed) | Long Lake Road to Square Lake Road | Troy | Reconstruction to a 3-lane road with a continuous center left-turn lane, drainage improvements, sewer/water improvements, curb/gutter installation, asphalt path (west side) and Americans with Disabilities Act- compliant sidewalks/crossings (east side). | Yes, southbound John R is closed | Southbound John R detour is South Blvd to Dequindre Rd, to Long Lake Rd, back to John R; northbound John R remains open to traffic | Dan's Excavating | 4/29/19 | Late fall | John R |
Lahser and 13 Mile Road intersection (PERMIT PROJECT) | Lahser Road and 13 Mile Road intersection | Beverly Hills | Consumers Energy high pressure gas main work | No, expect lane closures | No | Consumers Energy | 7/16/19 | Mid-September | Consumers Energy |
Livernois Road | From Avon Road to north of Walton | Rochester Hills | Reconstruction of road, improved drainage, traffic-signal modernization, upgrading sidewalks to comply with Americans with Disabilities Act, new guardrail, retaining wall repairs and replacing curbs and gutters | Yes, southbound Livernois is closed to traffic. Northbound Livernois will remain open to traffic | The detour for southbound Livernois traffic is Tienken Rd to Adams Rd to Avon Rd back to Livernois Rd | Pro-Line Asphalt | 6/21/19 | Late Fall | Livernois Road |
*Maple Road (PERMIT PROJECT & PART OF MDOT'S I-75 RECONSTRUCTION PROJECT) | Westbound Maple Road under I-75 | Troy | Westbound outside (right) lane of Maple Road is closed under I-75 for AT&T utility relocation; traffic shifted to the inside (left) lane in the work zone. | No; however, the WB outside (right) lane on Maple Road is closed under I-75; traffic shifted to inside (left) lane. | No | AT&T | 8/9/19 | 9/13/19 | MDOT Modernize 75 |
Maple Road and Middlebelt Road | Maple Road and Middlebelt Road intersection (roundabout construction)
| West Bloomfield Township | Construction of a roundabout, improved drainage, new watermain and Americans with Disabilities Act-compliant crosswalks. | Yes, intersection is expected to close in September | For detour routes: CLICK HERE | Angelo Iafrate | September, TBA | Late Fall | Maple and Middlebelt Roundabout Construction |
Maple Road Culvert (PART OF THE MAPLE AND MIDDLEBELT ROAD ROUNDABOUT CONSTRUCTION) | From Middlebelt Road to Inkster Road (culvert is between Glenway Drive and Bloomfield Glens Road) | West Bloomfield Township | Removal and replacement of a culvert under the road that carries Rouge River Tributary | Yes, Maple Road is closed between Middlebelt and Inkster roads | Inkster Rd to 14 Mile Rd to Middlebelt Rd, back to Maple Rd and vice versa | Angelo Iafrate | 6/29/19 | September, TBA | Maple Road Culvert |
Middlebelt Road (PERMIT PROJECT) | From 12 Mile Road to 13 Mile Road (emergency repair is just south of Orion Court) | Farmington Hills | Emergency road repairs | TBA | TBA | Office of the Oakland County Water Resources Commissioner | TBA | TBA | Traffic Alerts |
Milford Road | Just east of South Fenton Road and the railroad tracks | Rose Township | Culvert removal and replacement. Includes paving road, new guardrail and pavement markings | Yes, residential access will be maintained east of the culvert | Milford Rd to Clyde Rd to Hickory Ridge Rd to Fenton Rd, back to Milford Rd and vice versa | Zito Construction | 9/3/19 | Mid-October | Milord Road Culvert |
Oakwood Road | From M-15 to Leece Road | Ortonville, Groveland and Brandon townships | Resurfacing, right-turn lane extension from westbound Oakwood to northbound M-15, drainage improvements and Americans with Disabilities Act-compliant ramps and crosswalk on North Church Road at Oakwood Road | No; expect lane closures with flag control directing traffic when necessary | No | Ace-Saginaw Paving Company | July 15 | Late August | Federally Funded Overlays |
Opdyke Road | From Featherstone to Perry Street | Auburn Hills and Pontiac | Milling and resurfacing road with hot mix asphalt, Americans with Disabilities Act -compliant crosswalks/bus stops, improved drainage and new pedestrian path from Auburn Road to I-75 | No | No | Dan's Excavating | 4/22/19 | SUBSTANTIALLY COMPLETE (expect lane closures for behind the shoulder turf restoration) | Opdyke Road |
Preservation Overlays | Various heavier traveled roads throughout Oakland County | Various | Simple resurfacing, placing 2-2.5 inches of asphalt on the road surface; work is weather-dependent. | No | No | Cadillac Asphalt | 4/25/19 | September, TBA | Preservation Overlays |
Sashabaw Road | From Sherwood Road to Granger Road | Brandon Township | Pave gravel road with asphalt, improved drainage, shoulder paving in areas, curb and gutter installation in areas and storm sewer installation. | Yes; however, residential access will be maintained through the project | Sherwood Rd to Perry Lake Rd to Granger Rd, back to Sashabaw Rd and vice versa | Zito Construction | 7/1/19 | Late Fall | Sashabaw Road (Sherwood to Granger) |
Sashabaw Road (I-75 to Clarkston Road) | From I-75 to just south of Clarkston Road | Independence Township | Widening road to 5 lanes with a continuous left turn lane, resurfacing, right-turn lanes where warranted and Americans with Disabilities Act -compliant sidewalks and crosswalks. | No | No | Dan's Excavating | 4/22/18 | Late Fall | Sashabaw Road (I-75 to Clarkston) |
Spot Resurfacing | Various heavier traveled roads throughout Oakland County | Various | Milling short sections of roads and resurfacing with hot mix asphalt. | No | No | Cadillac Asphalt and Pro-Line Asphalt Paving | 4/22/19 | TBA | Spot Resurfacing |