The Road Commission for Oakland County (RCOC) expects to begin simple resurfacing work on Oakwood Road from M-15 to Leece Road in the Village of Ortonville and Brandon and Groveland townships on Monday, July 15.
The project is expected to be complete in late August.
During the work, the road will remain open to traffic; however, motorists can expect delays.
The approximately $565,000 project is funded by RCOC and federal road dollars purchased at a reduced rate from another county road agency in Michigan.
The two-mile project includes:
Milling sections of the road
Paving with asphalt
Extension of the westbound Oakwood Road right-turn lane to northbound M-15
Drainage improvements in a few areas
Americans with Disabilities Act-compliant crosswalk on North Church Street at Oakwood
New guardrail, signage and pavement markings
The contractor for the project is Ace-Saginaw Paving of Flint.