[ARCHIVED] RCOC WEEKLY ROAD CONSTRUCTION & PERMIT PROJECTS UPDATE (6/29-7/06)

road work sign

— The following projects may cause traffic delays on Road Commission for Oakland County (RCOC) roads between June 29 and July 6 or may start shortly thereafter.

It is RCOC’s goal to conduct road improvement projects in a way that interferes with traffic as little as possible. This list includes both Road Commission projects and projects conducted by others, under permit, on roads under the jurisdiction of the Road Commission.

Please note: This information is subject to change. Projects can change from day to day, and traffic delays can develop in a matter of minutes due to weather, emergency situations, etc.

The project list is attached. 


2018 Road Commission for Oakland County Road Construction and Permit Projects (6/29/18 update)

Road

Project Limits

Community or Communities

Project Description

Road Closure

Detour

Prime Contractor

Project Start

Anticipated Completion

Project Website

Baldwin Road (Phase I)

Phase I-Morgan Road to Gregory Road 2017-2018; Phase II-Gregory to Waldon 2018-2019

Orion Township

Reconstruction of Baldwin Road including: 5 roundabouts, widening, Americans with Disabilities Act (ADA) compliant crosswalks, improved lighting, pedestrian paths, concrete curb and gutter

No; intermittent lane closures (NB and SB Baldwin Road traffic maintained)

No

Dan's Excavating (Phase I contractor)

4/2/18

Late Fall (Phase II will begin Spring of 2019)

Baldwin Road

Gregory Road (part of the Baldwin Road Phase I project)

Gregory Road at Baldwin Road

Orion Township

Storm sewers, drainage, water main and pavement preparation

Yes

Baldwin Rd to Morgan Rd to Rohr Rd, back to Gregory Rd and vice versa

Dan's Excavating

5/14/18

Late August

Baldwin Road

Concrete Slab Replacements

Various heavier traveled roads

Various

Remove and replace concrete

No, expect lane closures

No

Chaperone

6/4/18

TBA

Concrete Slab Replacement

Dequindre Road (Phase II)

Burningbush Drive to Long Lake Road

Troy and Sterling Heights border

Widening to 5 lanes with center left-turn lane, traffic signal upgrades, improved drainage, Americans with Disabilities Act (ADA) compliant crosswalks

No

No

Dan's Excavating

3/5/18

Late Fall

Dequindre Road

*Square Lake Road (Part of the Dequindre Road project)

Square Lake (19 Mile) Road at Dequindre Road (ONLY WEST HALF OF INTERSECTION IS CLOSED)

Troy and Sterling Heights

Intersection paving

Yes, just the west half of Square Lake (19 Mile) Road at Dequindre Road

Click here for various detour routes

Dan's Excavating

5/21/18

6/29/18 (late evening)

Dequindre Road

Inkster Road

North of 14 Mile Road

Bloomfield Township and West Bloomfield Township

Repair of a failed roadside bank

Yes, just northbound Inkster is closed at 14 Mile Road. Southbound Inkster Road remains open to traffic.

14 Mile Rd to Middlebelt Rd to Maple Rd, back to Inkster Rd

RCOC

6/15/18 (emergency closure of northbound Inkster Rd)

TBA

Weekend, Emergency & Short-Term Road Closures

Joint Replacement

Various heavier traveled roads throughout Oakland County

Various

Milling out road joints and filling with hot mix asphalt

No; however, expect lane restrictions in work zones

No

Cadillac Asphalt

TBA

TBA

Road Joint Repairs

Maple Road (Phase II)

Halsted Road to Drake Road

West Bloomfield Township

Reconstruction including center turn lane, right turn lane extensions, drainage improvements, traffic-signal modernizations

Yes, westbound Maple Road is closed; however, 2-way traffic maintained between Drake and Ring roads (Henry Ford Hospital Entrance). Eastbound Maple Road remains open to traffic

Westbound Maple Road detour is Haggerty Rd to 14 Mile Rd to Drake Rd back to Maple Rd and vice versa

Dan's Excavating

4/9/18

Late July

Maple Road (Drake to Halsted)

*Halsted Road (part of the Maple Road Phase II project)

South half of intersection

West Bloomfield Township

Intersection improvements and paving

Yes, south leg of intersection

SB Halsted: EB Maple Rd to SB Drake Rd to WB 14 Mile Rd, back Halsted Rd. NB Halsted: WB 14 Mile Rd to SB Haggerty Rd to EB Maple Rd, back to Halsted Rd.

Dan's Excavating

6/11/18

Early July

Maple Road (Drake to Halsted)

Middlebelt Road (PERMIT PROJECT)

10 Mile Road and 14 Mile Road

Farmington Hills

Replacement of high pressure gas transmission line

No, currently under flag control from 9 a.m. - 3 p.m. daily

No

Consumers Energy

Late April

Late summer

Consumers Energy

Middlebelt Road (PERMIT PROJECT)

11 Mile and 12 Mile Road

Farmington Hills

Consumers Energy installation of high pressure gas main

Yes (local and emergency access maintained)

11 Mile Rd to Orchard Lake Rd to 12 Mile Rd, back to Middlebelt Rd and vice versa

Consumers Energy

6/16/18

8/10/18

Traffic Alerts

Napier Road

9 Mile to 10 Mile Road

Novi/Lyon Township border

Gravel road paving, improved drainage, paved shoulders and guardrail installation in necessary areas.

Yes (residential access maintained)

8 Mile Rd to Beck Rd to 10 Mile Rd, back to Napier Rd and vice versa.

Dan's Excavating

4/9/18

Mid-July

Napier Road

Opdyke Road

Auburn Road to Perry Road

Pontiac and Auburn Hills

Bridge replacement over the Clinton River, resurfacing, Americans with Disabilities Act compliant crosswalks/bus stops, improved drainage, construction of a pedestrian pathway from Auburn Rd to I-75 & water main work between Featherstone and Walton Blvd.

Yes, between Auburn Road and M-59 will close for bridge replacement, two-way traffic maintained from M-59 to Perry Road

Auburn Rd to Martin Luther King Blvd to Featherstone, back to Opdyke Rd and vice versa

Dan's Excavating

6/18/18

Mid-October

Opdyke Road

Preservation Overlays

Various heavier traveled roads throughout Oakland County

Various

Simple resurfacing, placing 1.5-2 inches of asphalt on the road surface; work is weather-dependent

No, mostly done under flag control

No

Ajax Paving

April

Various dates through the end of July

2018 Preservation Overlay (list and schedule)

*South Blvd.

Crooks Road to Adams Road

Rochester Hills and Troy

Resurfacing, drainage improvements, traffic signal upgrades and Borden Drain culvert replacement. South Blvd from Crooks to Coolidge will be partially reconstructed.

Yes, just west of Coolidge Hwy for culvert replacement. Once complete, the road will be open to westbound traffic from Coolidge to Adams, eastbound lanes will remain closed (date to be announced)

South Blvd. to Squirrel Rd to Square Lake Rd to Crooks Rd, back to South Blvd and vice versa.

Proline Asphalt

6/20/18

Mid-September

South Blvd.

Tripp Road

Van Road to Dixie Highway

Groveland Township

Reconstruction of road including culvert replacement, improved drainage, widening/paving of road shoulders, curb and gutter installation.

Yes, date to be announced

Dixie Hwy to Grange Hall Rd, back to Tripp Rd and vice versa

TBA

TBA

TBA

Tripp Road

Walton Blvd.

Adams Road and Squirrel Road

Auburn Hills and Rochester Hills

Replacement of three culverts, improved drainage, concrete curbs/gutters and resurfacing

No, two-way traffic is shifted to the north half of Walton Blvd. Firewood and Bellarmine drives are closed at Walton Blvd.

No, Firewood and Bellarmine drives are closed at Walton Blvd. Residents can use Tienken or Adams roads.

Z Contractors

5/14/18

Late fall (remaining resurfacing work could take place in 2019)

Walton Blvd Culvert Replacement

West Long Lake Road

Corporate Drive to Tower Drive

Troy

Concrete slab replacement

No, one lane maintained in each direction

No

Rigid Pavement Construction

6/18/18

Late July

Concrete Slab Replacement

West Long Lake Road

East and west approaches to Telegraph Road

Bloomfield Township

Remove West Long Lake Road concrete approaches at Telegraph Road and replace with asphalt

No, one lane maintained in each direction

No

Pro-Line Asphalt Paving Corporation

6/21/18

Late July

West Long Lake Road at Telegraph

Wood Trail (subdivision road)

South of Drahner, between M-24 and Newman Road

Oxford Township

Culvert replacement

Yes, closed to through vehicle traffic. Polly Ann Trail (a pedestrian/bike trail) is closed at Paint Creek

No set detour, residential traffic is maintained north and south of closure

Angelo Iafrate

5/21/18 (road closed since 2/24/18 due to a culvert failure)

Late July