Baldwin Road (Phase I) | Phase I-Morgan Road to Gregory Road 2017-2018; Phase II-Gregory to Waldon 2018-2019 | Orion Township | Reconstruction of Baldwin Road including: 5 roundabouts, widening, Americans with Disabilities Act (ADA) compliant crosswalks, improved lighting, pedestrian paths, concrete curb and gutter | No; intermittent lane closures (NB and SB Baldwin Road traffic maintained) | No | Dan's Excavating (Phase I contractor) | 4/2/18 | Late Fall (Phase II will begin Spring of 2019) | Baldwin Road |
Gregory Road (part of the Baldwin Road Phase I project) | Gregory Road at Baldwin Road | Orion Township | Storm sewers, drainage, water main and pavement preparation | Yes | Baldwin Rd to Morgan Rd to Rohr Rd, back to Gregory Rd and vice versa | Dan's Excavating | 5/14/18 | Late August | Baldwin Road |
Dequindre Road (Phase II) | Burningbush Drive to Long Lake Road | Troy and Sterling Heights border | Widening to 5 lanes with center left-turn lane, traffic signal upgrades, improved drainage, Americans with Disabilities Act (ADA) compliant crosswalks | No | No | Dan's Excavating | 3/5/18 | Late Fall | Dequindre Road |
Square Lake Road (Part of the Dequindre Road project) | Square Lake (19 Mile) Road at Dequindre Road (ONLY WEST HALF OF INTERSECTION WILL CLOSE) | Troy and Sterling Heights | Intersection paving | Yes, just the west half of Square Lake (19 Mile) Road at Dequindre | Click here for various detour routes | Dan's Excavating | 5/21/18 | 6/21/18 | Dequindre Road |
Haggerty Road (PERMIT PROJECT) | North of 12 Mile Road | Novi | Gas utility maintenance | No, southbound Haggerty Road outside (right) lane is closed | No | Consumers Energy | 5/17/18 | 5/25/18 | Consumers Energy |
Long Lake Road (PERMIT PROJECT) | Woodward (M-1) and Kensington Road | Bloomfield Hills | Canadian National (CN) railroad bridge repairs | No; however, left turns from Long Lake Rd to Kensington Rd will be temporarily prohibited | No | CN | 5/15/18 | 6/18/18 |
|
Maple Road (Phase II) | Halsted Road to Drake Road | West Bloomfield Township | Reconstruction including center turn lane, right turn lane extensions, drainage improvements, traffic-signal modernizations | Yes, westbound Maple Road is closed; however, 2-way traffic maintained between Drake and Ring roads (Henry Ford Hospital Entrance). Eastbound Maple Road will remain open to traffic. | Westbound Maple Road detour is Haggerty Rd to 14 Mile Rd to Drake Rd back to Maple Rd and vice versa | Dan's Excavating | 4/9/18 | Late July | Maple Road (Drake to Halsted) |
Halsted Road (part of the Maple Road Phase II project) | South leg of intersection | West Bloomfield Township | Intersection improvements and paving | Yes, south leg of intersection | TBA | Dan's Excavating | TBA | TBA | Maple Road (Drake to Halsted) |
Middlebelt Road (PERMIT PROJECT) | 10 Mile Road and 14 Mile Road | Farmington Hills | Replacement of high pressure gas transmission line | No, currently under flag control from 9 a.m. - 3 p.m. daily | No | Consumers Energy | Late April | Late summer | Consumers Energy |
Napier Road | 9 Mile to 10 Mile Road | Novi/Lyon Township border | Gravel road paving, improved drainage, paved shoulders and guardrail installation in necessary areas | Yes (residential access maintained) | 8 Mile Rd to Beck Rd to 10 Mile Rd, back to Napier Rd and vice versa. | Dan's Excavating | 4/9/18 | Mid-July | Napier Road |
Preservation Overlays | Various heavier traveled roads throughout Oakland County | Various | Simple resurfacing, placing 1.5-2 inches of asphalt on the road surface; work is weather-dependent | No, mostly done under flag control | No | Ajax Paving | April | July, TBA | 2018 Preservation Overlay (list and schedule) |
*South Blvd | Square Lake Road to just west of I-75 | Bloomfield Township | Concrete slab replacement | Yes (Georgetown Dr and Sheffield Rd traffic will be unable to access South Blvd) | South Blvd to Opdyke Rd to Square Lake Rd back to South Blvd and vice versa | Cipparone | 6/4/18 | Mid-June | Concrete Slab Replacement |
Tripp Road | Van Road to Dixie Highway | Groveland Township | Reconstruction of road including culvert replacement, improved drainage, widening/paving of road shoulders, curb and gutter installation. | Yes, date to be announced | Dixie Hwy to Grange Hall Rd, back to Tripp Rd and vice versa | TBA | TBA | TBA | Tripp Road |
Walton Blvd. | East of Squirrel Road | Auburn Hills | Replacement of three culverts, improved drainage, concrete curbs/gutters and resurfacing | No; however, inside (left) lane closures in both directions; two-way traffic shift to northbound side of road in late-May | No | Z Contractors | 5/14/18 | Late fall (remaining resurfacing work could take place in 2019) | Walton Blvd Culvert Replacement |
*West Long Lake Road | Corporate Drive to Tower Drive | Troy | Concrete slab replacement | No, one lane maintained in each direction | No | Rigid Pavement Construction | 6/18/18 | Late July | Concrete Slab Replacement |
*West Long Lake Road | East and west approaches to Telegraph Road | Bloomfield Township | Remove West Long Lake Road concrete approaches at Telegraph Road and replace with asphalt | No, one lane will be maintained in each direction | No | Pro-Line Asphalt Paving Corporation | TBA | TBA | TBA |
Wood Trail (subdivision road) | South of Drahner, between M-24 and Newman Road | Oxford Township | Culvert replacement | Yes, closed to through vehicle traffic. Polly Ann Trail (a pedestrian/bike trail) is closed at Paint Creek | No set detour, residential traffic is maintained north and south of closure | Angelo Iafrate Construction Company | 5/21/18 (road closed since 2/24/18 due to a culvert failure) | Late June | Weekend, Emergency & Short-Term Road Closures |