Baldwin Road (Phase I) | Phase I-Morgan Road to Gregory Road 2017-2018; Phase II-Gregory to Waldon 2018-2019 | Orion Township | Reconstruction of Baldwin Road including: 5 roundabouts, widening, Americans with Disabilities Act (ADA) compliant crosswalks, improved lighting, pedestrian paths, concrete curb and gutter | No; intermittent lane closures (NB and SB Baldwin Road traffic maintained) | No | Dan's Excavating (Phase I contractor) | 4/2/18 | Late Fall (Phase II will begin Spring of 2019) | Baldwin Road |
*Gregory Road (part of the Baldwin Road Phase I project) | Gregory Road at Baldwin Road | Orion Township | Storm sewers, drainage, water main and pavement preparation | Yes, Gregory Road will be closed at Baldwin Road | Baldwin Rd to Morgan Rd to Rohr Rd, back to Gregory Rd and vice versa | Dan's Excavating | 5/14/18 | TBA | Baldwin Road |
*Morgan Road (part of the Baldwin Road Phase I project) | Morgan Road at Baldwin Road | Orion Township | Storm sewers, drainage, water main and pavement preparation. | Yes, Morgan Road is closed at Baldwin Road **Will not be closed the same time as Gregory Road** | Baldwin Rd to Gregory Rd to Rohr Rd, back to Morgan Rd and vice versa | Dan's Excavating | 5/7/18 | 5/14/18 | Baldwin Road |
*Commerce Road | Orchard Lake Road and Hiller Road | West Bloomfield Township | Culvert replacement | Yes, the closure on Commerce Road is between the Dow Ridge Road subdivision entrances | Orchard Lake Rd to Cass Lake Rd to Cass Elizabeth Rd to Cooley Lake Rd to Hiller Road, back to Commerce Rd and vice versa | RCOC | 5/12/18 (in case of inclement weather, the back-up date is 5/13/18) | 5/12/18 | Weekend, Emergency & Short-Term Road Closures |
Concrete Slab Replacement | Various heavier traveled roads throughout Oakland County | Various | Removing sections of road and replacing with concrete; work is weather-dependent | Only lane closures; concrete can take up to 7 days to cure before allowing traffic back on repaired sections | No | TBA | TBA | TBA | 2018 Concrete Slab Replacement (list and schedule) |
*Davisburg Road | Ormond Road and Eagle Road | Rose Township | Culvert replacement | Yes, culvert is just east of Eagle and Forest Way roads | Ormond Rd to White Lake Rd to Milford Rd, back to Davisburg Rd and vice versa | RCOC | 5/13/18 | 5/13/18 | Weekend, Emergency & Short-Term Road Closures |
Dequindre Road (Phase II) | Burningbush Drive to Long Lake Road | Troy and Sterling Heights border | Widening to 5 lanes with center left-turn lane, traffic signal upgrades, improved drainage, Americans with Disabilities Act (ADA) compliant crosswalks | No | No | Dan's Excavating | 3/5/18 | Late Fall | Dequindre Road |
*East Commerce Road | Duck Lake Road and Carey Road | Commerce Township | Replacement of four culverts (two-day project) | Yes | Duck Lake Rd to Cooley Lake Rd to Carey Rd, back to East Commerce Rd and vice versa | RCOC | 5/19/18 | 5/20/18 | Weekend, Emergency & Short-Term Road Closures |
*Hickory Ridge Road | Fenton/South Holly Road and Clyde Road | Rose Township | Culvert replacement | Yes, culvert is located just north of Rose Center Road | Fenton Rd to Milford Rd to Clyde Rd, back to Hickory Ridge Rd and vice versa | RCOC | 5/19/18 (in case of inclement weather, the back-up date is 5/20/18) | 5/19/18 | Weekend, Emergency & Short-Term Road Closures |
*Hillsboro Road (PERMIT PROJECT) | Big Lake Road and Shaffer Road | Springfield Township | Consumers Energy gas service installation (project is south of Claypool Road) | Yes | Hillsboro Rd to Big Lake Rd to Shaffer Rd, back to Hillsboro and vice versa | CE Crews per Consumers Energy | 5/19/18 | 5/19/18 (evening) | Weekend, Emergency and Short-Term Closures |
*Long Lake Road (PERMIT PROJECT) | Woodward (M-1) and Kensington Road | Bloomfield Hills | Canadian National (CN) railroad bridge repairs | No; however, left turns from Long Lake Rd to Kensington Rd will be temporarily prohibited | No | CN | 5/14/18 | 6/18/18 | Traffic Alerts |
Maple Road (Phase II) | Halsted Road to Drake Road | West Bloomfield Township | Reconstruction including center turn lane, right turn lane extensions, drainage improvements, traffic-signal modernizations | Yes, westbound Maple Road is closed; however, 2-way traffic maintained between Drake and Ring roads (Henry Ford Hospital Entrance). Eastbound Maple Road will remain open to traffic. | Westbound Maple Road detour is Haggerty Rd to 14 Mile Rd to Drake Rd back to Maple Rd and vice versa | Dan's Excavating | 4/9/18 | Late July | Maple Road (Drake to Halsted) |
Halsted Road (part of the Maple Road Phase II project) | South leg of intersection | West Bloomfield Township | Intersection improvements and paving | Yes, south leg of intersection | TBA | Dan's Excavating | TBA | TBA | Maple Road (Drake to Halsted) |
Halsted Road (part of the Maple Road Phase II project) | North leg of intersection | West Bloomfield Township | Intersection improvements and paving | Yes, north leg of intersection | SB Halsted detour: WB Walnut Lake Rd to SB Haggerty Rd to EB Maple Rd, back to Halsted; NB Halsted detour: EB Maple Road to NB Drake Rd to WB Walnut Lake Rd, back to Halsted Rd | Dan's Excavating | 4/30/18 | Mid-May | Maple Road (Drake to Halsted) |
Napier Road | 9 Mile to 10 Mile Road | Novi/Lyon Township border | Gravel road paving, improved drainage, paved shoulders and guardrail installation in necessary areas. | Yes (residential access maintained) | 8 Mile Rd to Beck Rd to 10 Mile Rd, back to Napier Rd and vice versa. | Dan's Excavating | 4/9/18 | Mid-July | Napier Road |
Preservation Overlays | Various heavier traveled roads throughout Oakland County | Various | Simple resurfacing, placing 1.5-2 inches of asphalt on the road surface; work is weather-dependent | No, mostly done under flag control | No | Ajax Paving | April | Late summer | 2018 Preservation Overlay (list and schedule) |
Tripp Road | Van Road to Dixie Highway | Groveland Township | Reconstruction of road including culvert replacement, improved drainage, widening/paving of road shoulders, curb and gutter installation | Yes, date to be announced | Dixie Hwy to Grange Hall Rd, back to Tripp Rd and vice versa | TBA | TBA | TBA | Tripp Road |
*Walton Blvd. | East of Squirrel Road | Auburn Hills | Replacement of three culverts, improved drainage, concrete curbs/gutters and resurfacing | No; however, inside (left) lane closures in both directions; two-way traffic shift to northbound side of road in late-May | No | Z Contractors | 5/14/18 | Late Fall (remaining resurfacing work could take place in 2019) | Walton Blvd Culvert Replacement |
Wood Trail (subdivision road) | South of Drahner, between M-24 and Newman Road | Oxford Township | Culvert replacement | Yes, closed to through vehicle traffic. Polly Ann Trail (a pedestrian/bike trail) is closed on both sides of the road at Paint Creek | No set detour, residential traffic is maintained north and south of closure | Angelo Iafrate Construction Company | 2/24/18 Road closed due to culvert failure | TBA | Weekend, Emergency & Short-Term Road Closures |