[ARCHIVED] RCOC WEEKLY ROAD CONSTRUCTION AND PERMIT PROJECTS UPDATE (AUG 16-23)

Work Zone

The following projects may cause traffic delays on Road Commission for Oakland County (RCOC) roads between August 16 and August 23 or may start shortly thereafter.

It is RCOC’s goal to conduct road improvement projects in a way that interferes with traffic as little as possible. This list includes both Road Commission projects and projects conducted by others, under permit, on roads under the jurisdiction of the Road Commission.

Please note: This information is subject to change. Projects can change from day to day, and traffic delays can develop in a matter of minutes due to weather, emergency situations, etc.

The project list is also attached.                   


       

2017 Road Commission for Oakland County Road Construction and Permit Projects (8/16/17 Update)

Road

Project Limits

Community or Communities

Project Description

Road Closure

Detour

Prime Contractor

Project Start

Anticipated Completion

Project Website

*Cooley Lake Road (PERMIT PROJECT)
Burns Road and Duck Lake Road
Highland Township
Utility cut for gas pipeline
Yes
Duck Lake Rd to Commerce Rd to Burns Rd, back to Cooley Lake Rd and vice versa
Welded Construction
8/24/17
8/25/17
Traffic Alert
10 Mile Road (PERMIT PROJECT)
At Pierce Road (west of Greenfield Road)
Southfield
Water main, sanitary/storm sewer and pavement repairs (City of Southfield project)
Yes
Southfield Rd to Mt. Vernon Rd to Greenfield Rd back to 10 Mile and vice versa
Pamar Enterprises
6/16/17
9/11/17
City of Southfield Engineering Dept.
12 Mile Road
Haggerty Road and Farmington Road
Farmington Hills
Concrete slab replacement
12 Mile will have one lane open in each direction. South portion of  Drake 12/Mile Road intersection will close (date TBA)
Yes, for closure at Drake /12 Mile south portion of intersection is Drake to 11 Mile to Halsted back to 12 Mile and vice versa
Florence Cement
8/14/17
Mid November
12 Mile Road (Haggerty to Farmington)
12 Mile Road (BRIDGES)
Between Telegraph and Lahser roads
Southfield
Concrete repairs and partial painting
Intermittent lane restrictions in effect.
No
CA Hull
6/19/17
Late August
12 Mile Bridges/Southfield
Baldwin Road
Morgan Road to Waldon Road (2017-2019)
Orion Township
Reconstruction of Baldwin Road including: 5 roundabouts, widening, Americans with Disabilities Act (ADA) compliant crosswalks, improved lighting, pedestrian paths, concrete curb and gutter
No; temporary closures pending for water main and tree removal work
No
Dan's Excavating
7/18/17 (water main relocation and building demolition) Project will resume in the Spring of 2018 & 2019
Carryover project through 2019
Baldwin Road
Gregory Road (part of the Baldwin Road project)
At Baldwin Road
Orion Township
Water main replacement
Yes
Morgan Rd to Rohr Rd, back to Gregory Rd and vice versa
Dan's Excavating
9/14/17
10/5/17
Baldwin Road
Morgan Road (part of the Baldwin Road project)
At Baldwin Road
Orion Township
Water main replacement
Yes
Gregory Rd to Rohr Rd, back to Morgan Rd and vice versa
Dan's Excavating
8/21/17
9/14/17
Baldwin Road
Brown Road
Joslyn Road to M-24 (Lapeer Road)
Orion Township and Auburn Hills border
Concrete slab replacement
No
No
Cipparrone Contracting Inc.
8/24/17
9/18/17
Concrete Slab Replacement
Brown Road (PERMIT PROJECT)
Joslyn Road to Baldwin Road
Orion Township and Auburn Hills
Widening from current configuration to five-lanes (Orion Township project)
No, traffic will be maintained in both directions with continuous center left-turn lane
No
Pamar (per Orion Township)
7/18/17
Late Fall
Brown Road
Cass Lake Road
Orchard Lake Road and Otter Avenue
Keego Harbor
Concrete slab replacement
No; however, traffic can expect narrow lanes in work zones (truck traffic should seek alternate route)
No
Cipparrone Contracting Inc.
8/14/17
Early September
Concrete Slab Replacement
Dequindre Road (2-year project)
Burningbush Drive to Long Lake Road
Troy and Sterling Heights border
Widening to 5 lanes with center left-turn lane, traffic signal upgrades, improved drainage, Americans with Disabilities Act (ADA) compliant crosswalks
No, one lane will remain open each direction
No
TBA
TBA
TBA
Dequindre Road
Greenfield Road
9 Mile Road and 10 Mile Road
Southfield
Concrete slab replacement
No
No
Cipparrone Contracting Inc.
9/7/17
10/10/17
Concrete Slab Replacement
Haggerty Road
Haggerty Road/10 Mile intersection
Novi and Farmington Hills
Concrete slab replacement
No (lane closures throughout project)
No
Cipparrone Contracting Inc.
7/24/17
8/28/17
Concrete Slab Replacement
Lahser Road
11 Mile Road to Civic Center Drive
City of Southfield
Reconstruction (from Northwestern Hwy to Civic Center) and concrete patching (from 11 Mile to Northwestern Hwy)
Yes, Northwestern Hwy to Civic Center Drive (additional closures forthcoming)
Northwestern Hwy service drive to Civic Center Dr., back to Lahser and vice versa
Florence Cement
7/26/17
Mid September
Lahser Road
Maple Road (Phase I)
Haggerty Road to Halsted Road
West Bloomfield Township
Reconstruction including center turn lane, right turn lane extensions, drainage improvements, traffic-signal modernizations
Yes, westbound lane is closed. Eastbound lane will remain open to traffic
14 Mile Road for westbound traffic
Dan's Excavating
7/24/17
Mid November (Phase 2 from Halsted to Drake will begin Spring 2018)
Maple Road (Haggerty to Drake)
Middlebelt Road (BRIDGE OVER ROUGE RIVER)
Between 8 Mile Road and Grand River
Farmington Hills
Preventative maintenance including concrete replacement, deck repairs/sealing and repaving approaches and bridge with asphalt
No, lane restrictions throughout project
No
Z Contractors
8/7/17
Mid September
Middlebelt Bridge Over Rouge River
Napier Road/10 Mile Road
Intersection of Napier/10 Mile Road; including 10 Mile Road east and west of Napier Road (PHASE I)
Lyon Township and City of Novi
Reconstruction of intersection to a roundabout, hill cut on 10 Mile Road west of Napier and reconstruction of 10 Mile from Copperwood to Nepavine Dr.
Yes, closed from Copperwood to Nepavine on 10 Mile Road, including intersection
Griswold Rd to 8 Mile Rd to Beck Rd, back to 10 Mile Road and vice versa
Dan's Excavating
7/17/17
Mid-October (road to fully reopen; continued work through mid-November)
Napier/10 Mile Road
Orchard Lake Road
North of Northwestern Hwy. to just south of Maple Road
West Bloomfield Township
Reconstruction of road to a 4-lane boulevard, elimination of service drive east of Orchard Lake Rd, construction of pedestrian paths, ADA compliant crosswalks, improved drainage
No, one lane open in each direction with a center left-turn lane (Powers Rd intersection will close for realignment at a date TBA)
No
Dan's Excavating
6/12/17
Late October
Orchard Lake Road Construction
Sashabaw Road
Maybee Road to Waldon Road
Independence Township
Concrete slab replacement
No
No
Cipparrone Contracting Inc.
7/27/17
8/30/17
Concrete Slab Replacement
South Blvd. (PAVING)
East of John R to west of Dequindre
Rochester Hills and Troy border
Resurfacing
No, under flag control
No
Cadillac Asphalt
6/20/17
Mainline paving complete; striping and restoration work ongoing
South Boulevard
South Blvd./ Livernois Road intersection
South Blvd./ Livernois Road
Rochester Hills and Troy border
Intersection safety improvement project includes widening, new traffic signal, ADA-compliant crosswalks and resurfacing
No, intersection is open to traffic with lane restrictions. Traffic signal is moving one approach at a time for duration of project
No
Florence Cement
5/8/17
Mid September
South Boulevard
Stadium Drive (PERMIT PROJECT)
East of Lapeer Road (M-24)
Orion Township
Remove and replace a section of Stadium Drive
Yes
Lapeer Rd to Scripps Rd to Bald Mountain Rd, back to Stadium Dr & vice versa
OHM Advisors
8/7/17
Late August
Orion Township
Traymore Drive (PERMIT PROJECT)
South of Highland Avenue
Bloomfield Township
Storm drain construction and paving
Yes
Highland Ave to Winthrop Rd to Hillsdale Rd to Marlborough Dr, back to Traymore Dr and vice versa
ADJ Excavating (per the Office of the Oakland County Water Resources Commissioner)
7/12/17
Late August
OCWRC
Walnut Lake Road
West of Orchard Lake Road
West Bloomfield Township
Culvert replacement; work is weather-dependent
Yes
Orchard Lake Rd to Maple Rd to Farmington Rd, back to Walnut Lake Rd and vice versa
Commerce Construction
TBA
TBA
RCOC Weekend Road Closures

             

Road & Permit Projects List Aug. 16-23