Posted on: May 31, 2017

[ARCHIVED] RCOC WEEKLY ROAD CONSTRUCTION AND PERMIT PROJECTS UPDATE (MAY 31-JUNE 7)

Work Zone

      The following projects may cause traffic delays on Road Commission for Oakland County (RCOC) roads between May 31 and June 7 or may start shortly thereafter.

      It is RCOC’s goal to conduct road improvement projects in a way that interferes with traffic as little as possible. This list includes both Road Commission projects and projects conducted by others, under permit, on roads under the jurisdiction of the Road Commission.

       Please note: This information is subject to change. Projects can change from day to day, and traffic delays can develop in a matter of minutes due to weather, emergency situations, etc.

      The project list is attached.                      

Road Commission for Oakland County Road Construction and Permit Projects (5/31/17 update)

Road

Project Limits

Community or Communities

Project Description

Road Closure

Detour

Prime Contractor

Project Start

Anticipated Completion

Project Website

Baldwin Road
Seymour Lake Road to Oakwood Road
Brandon and Oxford townships
Milling and resurfacing road
No, flaggers will direct traffic
No
Ace-Saginaw Paving Company
6/1/17
Mid-June
Preservation Overlays
Brown Road (PERMIT PROJECT)
Joslyn Road to Baldwin Road
Orion Township and Auburn Hills
Widening  from current configuration to five-lanes
No, traffic will be maintained in both directions with continuous center left-turn lane
No
Orion Township and OHM Advisors
TBA (July)
TBA
Brown Road
Crooks Road
Square Lake Road to south of Long Lake Road
Troy
Concrete slab replacement on turn-arounds and travel lanes
No
No
DiLisio
Early June
Late June
City of Troy Public Works
Giddings Road
Silverbell Road to Waldon Road
Orion Township
Preservation overlay; pulverizing road surface and resurfacing with 2 inches of asphalt
No, flaggers will direct traffic
No
Ajax
5/30/17
6/1/17
Preservation Overlays
Lahser Road
Maple Road to Long Lake Road
Bloomfield Township and Bloomfield Hills
Preservation 
No
No
Ajax
5/16/17
COMPLETE
Preservation Overlays
Lakeville Road
Rochester Road to Glaspie Road
Village of Oxford, Oxford and Addison townships
Milling, resurfacing and some guardrail replacement
No, flaggers directing traffic
No
Ace-Saginaw Paving Company
5/15/17
Early June
Preservation Overlays
Maple Road
Farmington Road to Orchard Lake Road
West Bloomfield Township
Reconstruction including center turn lane, right turn lane extensions, drainage improvements, traffic-signal modernizations.
Yes, eastbound lane is closed; westbound lane remains open
Drake Rd to Walnut Lake Rd to Orchard Lake Rd and vice versa
Dan’s Excavating
4/3/2017
Late July
Maple Road Project
Oakwood Road
Leece Road to M-24
Brandon and Oxford townships
Milling and resurfacing
No, flaggers will direct traffic.
No
Ace-Saginaw Paving Company
TBA
TBA
Preservation Overlays
Orchard Lake Road
North of Northwestern Hwy. to just south of Maple Road
West Bloomfield Township
Reconstruction of road to a 4-lane boulevard, elimination of service drive east of Orchard Lake Rd, construction of pedestrian paths, ADA compliant crosswalks, improved drainage
No, one lane open in each direction with a center left-turn lane (Powers Rd intersection will close for realignment at a date TBA)
No
Dan’s Excavating
6/12/17 (utility relocation work in progress)
Late October
Orchard Lake Road Construction
South Blvd./ Livernois Road intersection
South Blvd./ Livernois Road
Rochester Hills and Troy border
Intersection safety improvement project includes widening, new traffic signal, ADA compliant cross walks and resurfacing
No, intersection is open to traffic. Traffic signal is moving one approach at a time for duration of project
No
Florence Cement
5/8/17
Mid-September
South Boulevard
Summer Road (PERMIT PROJECT)
East of M-24 (Lapeer Road)
Orion Township
Summer Road closed at M-24 for installation of underground utilities for Kroger
Yes (residential road)
Residents are using Glanworth or Goldengate roads
Oscar W. Larson Company
5/22/17
6/5/17
Oscar W. Larson
Williams Lake Road
Elizabeth Lake Road to Pontiac Lake Road
Waterford Township
Micro-milling, chip and seal and complete with an asphalt overlay
No, flaggers directing traffic
No
Cadillac Asphalt
5/15/17
End of June
Preservation Overlays

                  

5/31 RCOC ROAD CONSTRUCTION & PERMIT PROJECTS LIST