Posted on: June 30, 2023

[ARCHIVED] PROJECTS THAT COULD DELAY TRAFFIC ON RCOC ROADS JUNE 30 AND JULY 7 OR MIGHT START SHORTLY THEREAFTER

Road Commission for Oakland County Construction Update Road to 2023 image

The following projects may cause traffic delays on Road Commission for Oakland County (RCOC) roads between June 30 and July 7 or may start shortly thereafter. 

It is RCOC’s goal to conduct road improvement projects in a way that interferes with traffic as little as possible. This list includes both Road Commission projects and projects conducted by others, under permit, on roads under the jurisdiction of the Road Commission.

Please note: This information is subject to change. Projects can change from day to day, and traffic delays can develop in a matter of minutes due to weather, emergency situations, etc.

The project list is attached.                                         

Additional information about current and upcoming projects can also be viewed on the RCOC website:   RCOC 2023 Road Construction  (http://www.rcocweb.org/189/Road-Projects).  

 RCOC Road Construction and Permit Projects (6/30/23 update)

ROAD

PROJECT LIMITS

COMMUNITY

PROJECT DESCRIPTION

CLOSURE

DETOUR

CONTRACTOR

PROJECT START

ESTIMATED COMPLETION

PROJECT INFORMATION

Cooley Lake Road culvert replacement over the Huron River

Carroll Lake Road to Bogie Lake Road

Commerce Township and White Lake Township

Replace culverts with pre-cast concrete bridge, asphalt paving in the vicinity of the new bridge, new guardrail, storm sewer/drainage improvements and new concrete curbs and gutters in the vicinity of the bridge.

Yes, the road will close on July 10. Residential access maintained east and west of the work.

Carroll Lake Rd to Wise Rd to Bogie Lake Rd, back to Cooley Lake Rd and vice versa.

Anlaan Construction

7/10

Late October

Cooley Lake Road Culvert Replacement

East Avon Road, Dequindre Road to 23 Mile Road (PERMIT PROJECT)

23 Mile Road and Dequindre Road

Rochester Hills and Shelby Township

Great Lakes Water Authority (GLWA) water infrastructure improvements. The project includes reconstruction and widening of East Avon Rd and roundabout construction at 23 Mile and Dequindre Rd

Yes.

Dequindre Rd to Hamlin Rd to Ryan Rd to Shelby Rd to 24 Mile Rd, back to Dequindre Rd and vice versa.

GLWA

12/5/22

Mid-August

Great Lakes Water Authority

Elizabeth Lake Road/Oxbow Lake Road intersection (PHASE 2)

Elizabeth Lake Road/Oxbow Lake Road intersection and resurfacing work on Elizabeth Lake Road from Teggerdine Road to Oxbow Lake Road

White Lake Township

Single-lane roundabout construction with improved drainage, Americans with Disabilities Act-compliant crosswalks, sidewalks, asphalt paving at the roundabout, street lighting, resurfacing between the two roundabouts, and curb and gutter installation.

Yes, the intersection is closed.

Elizabeth Lake Rd to Pontiac Lake Rd to Highland Rd (M-59) to Bogie Lake Rd to Cooley Lake Rd to Oxbow Lake Rd, back to Elizabeth Lake Rd and vice versa.

Fonson Company Inc.

6/19

Early September

Elizabeth Lake Road Roundabouts (White Lake Township)

Fourteen Mile Road

Barrington Road to Dequindre Road

Madison Heights and Troy

Asphalt resurfacing, concrete repairs, minor drainage improvements, Americans with Disabilities Act-compliant crosswalks, traffic signal upgrades, and repairs to curbs and gutters..

No, expect lane closures.

No.

Florence Cement

3/6

Mid-August

Fourteen Mile Road, Barrington to Dequindre Road

Greenfield Road/ Normandy Road/ Beverly Road intersection

Greenfield Road/ Normandy Road/ Beverly Road intersection

Village of Beverly Hills and Royal Oak

Construction of a "compact" one-lane roundabout, reconstruction of .19 miles of Normandy and Greenfield roads, drainage improvements, new sidewalks, permanent closure of Beverly Court at Greenfield Road, and new curbs and gutters.

Yes, the intersection is closed.

For detours, visit https://www.rcocweb.org/655/GreenfieldNormandy-Beverly-Roundabout

DiPonio Contracting

6/12

Late August

Greenfield/Normandy/Beverly Roundabout

Milford Road

Just south of the entrance to Kensington Park/Huron River Parkway

Milford Township

Consumers Energy replacement of a 24-inch gas transmission line below the road's surface.

Yes

General Motors Rd to Hickory Ridge Rd to Stobart Rd to Kensington Rd to Grand River Ave, back to Milford Rd and vice versa. Business access maintained during the closure.

Consumers Energy

7/6

7/16

Consumers Energy

Novi Road

Nine Mile Road to Ten Mile Road

Novi

Asphalt resurfacing, some widening, Americans with Disabilities Act-compliant crosswalks, culvert/sewer crossing replacements, drainage improvements, traffic signal upgrades, concrete replacement and left-turn lane extension south of 10 Mile Rd.

Yes, northbound Novi Rd is closed. Southbound Novi Rd is open to traffic for the project’s duration.

The detour for the northbound closure is Nine Mile Rd to Meadowbrook Rd to Ten Mile Rd, back to Novi Rd. Residential and business access maintained.

Springline Excavating LLC

3/20

Late fall

Novi Road, Nine Mile to Ten Mile Road

Oakwood Road/Hadley Road intersection

Oakwood Road/Hadley Road intersection

Brandon Township

Intersection safety improvements including extending some turn lanes on Oakwood Rd, replacement of culvert under the road, widening Oakwood Rd shoulders, storm sewer/drainage improvements, new curbs and gutters. 

The intersection is closed.

Oakwood Rd traffic detour is Baldwin Rd to Seymour Lake Rd to Ortonville Rd (M-15) back to Oakwood Rd and vice versa. Hadley Rd detour is Seymour Lake Rd to Ortonville Rd (M-15) to Hegel Rd, back to Hadley Rd and vice versa.

Zito Construction

6/19

Early September

Oakwood Road/Hadley Road intersection

Orchard Lake Road

Middlebelt Road to south of Commerce Road

Keego Harbor, Orchard Lake Village, Sylvan Lake and West Bloomfield Township

Paving with asphalt, converting the road to three through lanes with a continuous center left turn-lane, some reconstruction, sidewalk upgrades, Americans with Disabilities Act-compliant crosswalks and traffic signal upgrades.

Yes, Commerce Rd at Orchard Lake Rd will close. NB/EB Orchard Lake Rd, Commerce Rd to Rycroft St will close (SB and WB Orchard Lake Rd will remain open).

Commerce Rd detour is Hiller Rd to Cooley Lake Rd to Cass Elizabeth Rd to Cass Lake Rd, back to Orchard Lake Rd and vice versa. NB/EB Orchard Lake Rd detour is Long Lake Rd to Middlebelt Rd, back to Orchard Lake Rd.

Cadillac Asphalt

July 6

Mid-November

Orchard Lake Road, Commerce Road to Middlebelt Road

Orchard Lake Road (part of the Orchard Lake Road project, south of Commerce Road to Middlebelt Road)

Commerce Road to Rycroft Street

Orchard Lake Village and Keego Harbor

Reconstruction of the road and drainage improvements.

NB/EB Orchard Lake Rd to close from Commerce Rd to Rycroft St. SB/WB Orchard Lake Rd will remain open to traffic.

NB and EB traffic detour is Long Lake Rd to Middlebelt Rd , back to Orchard Lake Rd.

Cadillac Asphalt

July 6

Early September

Orchard Lake Road, Commerce Road to Middlebelt Road

Commerce Road at Orchard Lake Road  (part of the Orchard Lake Road construction, south of Commerce Road to Middlebelt Road)

Commerce Road at Orchard Lake Road.

Orchard Lake Village and Keego Harbor

Intersection reconstruction.

Yes, Commerce Rd at Orchard Lake Rd will close for approximately 35 days starting July 6.

Orchard Lake Rd/Commerce Rd detours: NB/EB Orchard Lake Rd is Long Lake Rd to Middlebelt Rd, back to Orchard Lake Rd. Commerce Rd detour is Hiller Rd to Cooley Lake Rd to Cass Elizabeth Rd to Cass Lake Rd, back Orchard Lake Rd and vice versa.

Cadillac Asphalt

July 6

August 9

Orchard Lake Road, Commerce Road to Middlebelt Road

Preservation Overlays (Simple Resurfacing)

Various heavier traveled roads throughout Oakland County

Various

Simple resurfacing with placing 2-2.5 inches of asphalt on the road surface; work is weather-dependent.

No, expect traffic delays. At least one lane will remain open on each road during the work, with flaggers directing traffic.

No

Cadillac Asphalt and Ace-Saginaw Paving

4/25

Fall, TBA

Simple Resurfacing (Preservation Overlays)

Spot Resurfacing

Various heavier traveled roads in Oakland County

Various

Milling (grinding) of pavement on smaller sections of roads and paving with asphalt. Paving work is weather-dependent.

No, work is done with flaggers directing traffic

No

Florence Cement and Pro-Line Asphalt

5/2

TBA

Spot Resurfacing

Ten Mile Road (PHASE 2)

Haggerty Road to Meadowbrook Road

Novi

Resurfacing with asphalt, safety improvements (continuous center left-turn lane), Americans with Disabilities Act-compliant crosswalks, sidewalk on the south side of Ten Mile Rd, traffic signal upgrades, shoulder widening, curb and gutter repairs/replacement.

Yes, the road is closed to westbound traffic and remains open to eastbound traffic. Business and residential access maintained.

Westbound traffic detour is Haggerty Rd to Grand River Ave to Meadowbrook Rd, back to Ten Mile Rd.

Toebe Construction

5/22

Fall (the road is expected to reopen to two-way traffic approximately mid-Aug.; lane closures will continue for paving into Sept.)

Ten Mile Road

Twelve Mile Road (PERMIT PROJECT)

Dartmouth Road to Stephenson Hwy.

Madison Heights

MDOT is constructing a diverging diamond interchange in conjunction with I-75 construction, 8 Mile Rd (M-102) to north of 13 Mile Road.

Yes

12 Mile Rd to John R Rd to 13 Mile Rd to Stephenson Hwy., back to 12 Mile Rd and vice versa.

MDOT

2/24

8/31

Modernize 75

Waldon Road (PHASE 1)

Baldwin Road to Clintonville Road

Independence Township and Orion Township

Two-year project that includes gravel road paving with asphalt, replacement of culverts, shared-use pathway along a section of Waldon Rd, paved road shoulders and stream improvement. A roundabout at 

Clintonville Rd/Waldon Rd will be built in 2024.

Yes, the road is closed. Access to homes and businesses maintained.

Baldwin Rd to Maybee Rd to Clintonville Rd, back to Waldon Rd and vice versa.

Dan's Excavating

6/19

Mid-November (Phase 2 construction will start in early 2024, date TBA)

Waldon Road, Clintonville to Baldwin Road

Walton Blvd.

Clintonville Road to the Pontiac city limits

Waterford Township

Removal of pavement, paving with asphalt, some curb/gutter repairs, traffic signal upgrade at Walton/Silver Lake Rd intersection and Americans with Disabilities Act-compliant crosswalks.

Two-way traffic maintained on Walton Blvd throughout the project. Silver Lake Rd will close at Walton Blvd. (date TBA) for approximately 21 days.

Silver Lake Rd closure at Walton Blvd. starting late July (date TBA) detours are: EB Walton Blvd to Silver Lake Rd is Sashabaw Rd to Dixie Hwy to Silver Lake Rd. WB Walton Blvd to Silver Lake Rd is Telegraph Rd to Dixie Hwy to Silver Lake Rd.

Florence Cement

6/6

Mid-November

Walton Blvd., Clintonville Road to the Pontiac city limits

 TBA (To Be Announced)