Posted on: June 5, 2023

[ARCHIVED] PROJECTS THAT COULD DELAY TRAFFIC ON RCOC ROADS JUNE 5 AND JUNE 9 OR MIGHT START SHORTLY THEREAFTER

Road Commission for Oakland County Construction Update Road to 2023 image

The following projects may cause traffic delays on Road Commission for Oakland County (RCOC) roads between June 5 and June 9 or may start shortly thereafter. 

It is RCOC’s goal to conduct road improvement projects in a way that interferes with traffic as little as possible. This list includes both Road Commission projects and projects conducted by others, under permit, on roads under the jurisdiction of the Road Commission.

Please note: This information is subject to change. Projects can change from day to day, and traffic delays can develop in a matter of minutes due to weather, emergency situations, etc.

The project list is attached.                                         

Additional information about current and upcoming projects can also be viewed on the RCOC website:   RCOC 2023 Road Construction  (http://www.rcocweb.org/189/Road-Projects).  

RCOC Road Construction and Permit Projects (6/5/23 update)

ROAD

PROJECT LIMITS

COMMUNITY

PROJECT DESCRIPTION

CLOSURE

DETOUR

CONTRACTOR

PROJECT START

ESTIMATED COMPLETION

PROJECT INFORMATION

Clarkston Road (PERMIT PROJECT)

Adams Road to Lake George Road

Oakland Township

Drainage improvements, storm sewer installation and gravel road paving by private developers.

Yes. Residential and business access maintained throughout construction.

Lake George Rd to Stoney Creek Rd to Adams Rd, back to Clarkston Rd and vice versa.

Ajax Paving

4/10

Late June

Permit Work, Short-Term Work & Road Closures

Cooley Lake Road culvert replacement over the Huron River

Carroll Lake Road to Bogie Lake Road

Commerce Township and White Lake Township

Replace culverts with pre-cast concrete bridge, asphalt paving in the vicinity of the new bridge, new guardrail, storm sewer/drainage improvements and new concrete curbs and gutters in the vicinity of the bridge.

Yes, the road will close. Residential access maintained east and west of the work.

Carroll Lake Rd to Wise Rd to Bogie Lake Rd, back to Cooley Lake Rd and vice versa.

Anlaan Construction

July, TBA

Late October

Cooley Lake Road Culvert Replacement

East Avon Road, Dequindre Road to 23 Mile Road (PERMIT PROJECT)

23 Mile Road and Dequindre Road

Rochester Hills and Shelby Township

Great Lakes Water Authority (GLWA) water infrastructure improvements. The project includes reconstruction and widening of East Avon Rd and roundabout construction at 23 Mile and Dequindre Rd.

Yes.

Dequindre Rd to Hamlin Rd to Ryan Rd to Shelby Rd to 24 Mile Rd, back to Dequindre Rd and vice versa.

GLWA

12/5/22

Mid-August

Great Lakes Water Authority

Elizabeth Lake Road/ Teggerdine Road intersection (PHASE 1)

Elizabeth Lake Road/ Teggerdine Road intersection

White Lake Township

Single-lane roundabout construction with improved drainage, Americans with Disabilities Act-compliant crosswalks, sidewalks, asphalt paving at the roundabout, street lighting, installation of some curbs and gutters.

Yes, the intersection is closed to traffic.

Elizabeth Lake Rd to Pontiac Lake Rd to Highland Rd (M-59) to Bogie Lake Rd to Cooley Lake Rd to Oxbow Lake Rd, back to Elizabeth Lake Rd and vice versa.

Fonson Company Inc.

3/13

Early June

Elizabeth Lake Road Roundabouts (White Lake Township)

Elizabeth Lake Road/Oxbow Lake Road intersection (PHASE 2)

Elizabeth Lake Road/Oxbow Lake Road intersection and resurfacing work on Elizabeth Lake Road from Teggerdine Road to Oxbow Lake Road

White Lake Township

Single-lane roundabout construction with improved drainage, Americans with Disabilities Act-compliant crosswalks, sidewalks, asphalt paving at the roundabout, street lighting, resurfacing between the two roundabouts, curb and gutter installation.

 

 

 

Yes, the intersection will close to traffic once roundabout construction is completed at Elizabeth Lake Rd/Teggerdine Rd intersection and after school is out.

Elizabeth Lake Rd to Pontiac Lake Rd to Highland Rd (M-59) to Bogie Lake Rd to Cooley Lake Rd to Oxbow Lake Rd, back to Elizabeth Lake Rd and vice versa.

Fonson Company Inc.

June, TBA (after completion of the current school year and the roundabout construction at Elizabeth Lake Rd/Teggerdine Rd)

Early September

Elizabeth Lake Road Roundabouts (White Lake Township)

Fourteen Mile Road

Barrington Road to Dequindre Road

Madison Heights and Troy

Asphalt resurfacing, concrete repairs, minor drainage improvements, Americans with Disabilities Act-compliant crosswalks, traffic signal upgrades, repairs to curbs and gutters.

No, expect lane closures.

No.

Florence Cement

3/6

Mid-August

Fourteen Mile Road, Barrington to Dequindre Road

Greenfield Road/ Normandy Road/ Beverly Road intersection

Greenfield Road/ Normandy Road/ Beverly Road intersection

Village of Beverly Hills and Royal Oak

Construction of a "compact" one-lane roundabout, reconstruction of .19 miles of Normandy and Greenfield roads, drainage improvements, new sidewalks on Greenfield/Normandy/Beverly roads, permanent closure of Beverly Court at Greenfield Road, new curbs and gutters.

Yes

For detours, visit https://www.rcocweb.org/655/GreenfieldNormandy-Beverly-Roundabout

DiPonio Contracting

6/12

Late August

Greenfield/Normandy/Beverly Roundabout

*Livernois Road (PERMIT PROJECT)

Northbound Livernois Road, Auburn Road to Hamlin Road (southbound Livernois Road will remain open to traffic)

Rochester Hills

Road widening and approach construction to facilitate private development.

Yes, northbound Livernois Rd is closed to traffic. Southbound Livernois Rd will remain open to traffic.

Northbound Livernois Rd detour is Auburn Rd to Crooks Rd to Hamlin Rd, back to Livernois Rd.

East Edge Excavating on behalf of OKY Construction

5/17

Mid-June

Permit Work, Short-Term Work & Road Closures

*Novi Road

Nine Mile Road to Ten Mile Road

Novi

Asphalt resurfacing, some widening, Americans with Disabilities Act-compliant crosswalks, culvert/sewer crossing replacements, drainage improvements, traffic signal upgrades, concrete replacement and left-turn lane extension south of 10 Mile Rd.

 

Northbound Novi Rd is closed to traffic. Southbound Novi Rd is open for the duration of the project. 

The detour for the northbound closure is Nine Mile Rd to Meadowbrook Rd to Ten Mile Rd, back to Novi Rd. Residential and business access maintained.

Springline Excavating LLC

3/20

Late fall

Novi Road, Nine Mile to Ten Mile Road

*Oakwood Road/Hadley Road intersection

Oakwood Road/Hadley Road intersection

Brandon Township

Intersection safety improvements including extending some turn lanes on Oakwood Rd, replacing a culvert under the road, widening Oakwood Rd shoulders, storm sewer/drainage improvements, new curbs and gutters.

The intersection will close to traffic on June 19.

Oakwood Rd traffic detour is Baldwin Rd to Seymour Lake Rd to Ortonville Rd (M-15) back to Oakwood Rd and vice versa. Hadley Rd detour is Seymour Lake Rd to Ortonville Rd (M-15) to Hegel Rd, back to Hadley Rd and vice versa.

Zito Construction

6/19

Early September

Oakwood Road/Hadley Road intersection

Preservation Overlays (Simple Resurfacing)

Various heavier traveled roads throughout Oakland County

Various

Simple resurfacing with placing 2-2.5 inches of asphalt on the road surface; work is weather-dependent.

No, expect traffic delays. At least one lane will remain open on each road during the work with flaggers directing traffic.

 

 

No

Cadillac Asphalt and Ace-Saginaw Paving

4/25

Fall, TBA

Simple Resurfacing (Preservation Overlays)

Spot Resurfacing

Various heavier traveled roads in Oakland County

Various

Milling (grinding) of pavement on smaller sections of roads and paving with asphalt. Paving work is weather-dependent

No, work is done with flaggers directing traffic

No

Florence Cement and Pro-Line Asphalt

5/2

TBA

Spot Resurfacing

Ten Mile Road (PHASE 2)

Haggerty Road to Meadowbrook Road

Novi

Resurfacing with asphalt, safety improvements (continuous center left-turn lane), Americans with Disabilities Act-compliant crosswalks, sidewalk on the south side of Ten Mile Rd, traffic signal upgrades, shoulder widening, curb and gutter repairs/replacement.

Yes, the road is closed to westbound traffic and remains open to eastbound traffic. Business and residential access maintained.

Westbound traffic detour is Haggerty Rd to Grand River Ave to Meadowbrook Rd, back to Ten Mile Rd.

Toebe Construction

5/22

Fall (the road is expected to reopen to two-way traffic approximately mid-Aug.; lane closures will continue for paving into Sept.)

Ten Mile Road

Twelve Mile Road (PERMIT PROJECT)

Dartmouth Road to Stephenson Hwy.

Madison Heights

MDOT is constructing a diverging diamond interchange in conjunction with I-75 construction, 8 Mile Rd (M-102) to north of 13 Mile Road.

Yes

12 Mile Rd to John R Rd to 13 Mile Rd to Stephenson Hwy., back to 12 Mile Rd and vice versa.

MDOT

2/24

8/31

Modernize 75

*Union Lake Road

Just north of Willow Road

Commerce Township

Consumers Energy gas main repairs.

Yes. Access to businesses maintained.

Commerce Rd to South Commerce Rd/Carroll Lake Rd to Wise Rd, back to Union Lake Rd and vice versa.

Consumers Energy

6/5

6/12

Consumers Energy

Waldon Road (PERMIT PROJECT)

Baldwin Road to Clintonville Road

Independence Township and Orion Township

Utility relocation is being done before gravel road paving and roundabout construction at Waldon Road and Clintonville Road.

No, expect periodic lane closures with flaggers directing traffic.

No

Various utilities

3/6

TBA

Waldon Road, Clintonville to Baldwin Road

Walton Blvd.

Clintonville Road to the Pontiac city limits

Waterford Township

Removal of pavement, paving with asphalt, some curb/gutter repairs, traffic signal upgrade at Walton/Silver Lake Rd intersection and Americans with Disabilities Act-compliant crosswalks.

Two-way traffic maintained on Walton Blvd throughout the project. Silver Lake Rd will close at Walton Blvd. starting July 6 for approximately 21 days.

Silver Lake Rd closure at Walton Blvd. on July 6 detours are: EB Walton Blvd to Silver Lake Rd is Sashabaw Rd to Dixie Hwy to Silver Lake Rd. WB Walton Blvd to Silver Lake Rd is Telegraph Rd to Dixie Hwy to Silver Lake Rd.

Florence Cement

6/6

Mid-November

Walton Blvd., Clintonville Road to the Pontiac city limits

 

3 *indicates a new or updated project; TBA (To Be Announced)