[ARCHIVED] PROJECTS THAT COULD DELAY TRAFFIC ON RCOC ROADS MAR. 31 & APR. 7 OR MIGHT START SHORTLY THEREAFTER

Construction update image

The following projects may cause traffic delays on Road Commission for Oakland County (RCOC) roads between March 31and April 7 or may start shortly thereafter. 

It is RCOC’s goal to conduct road improvement projects in a way that interferes with traffic as little as possible. This list includes both Road Commission projects and projects conducted by others, under permit, on roads under the jurisdiction of the Road Commission.

Please note: This information is subject to change. Projects can change from day to day, and traffic delays can develop in a matter of minutes due to weather, emergency situations, etc.

The project list is attached.                                        

Additional information about current and upcoming projects can also be viewed on the RCOC website:   RCOC 2023 Road Construction  (http://www.rcocweb.org/189/Road-Projects).          


 

 

 

RCOC Road Construction and Permit Projects (3/31/23 update)

ROAD

PROJECT LIMITS

COMMUNITY

PROJECT DESCRIPTION

CLOSURE

DETOUR

CONTRACTOR

PROJECT START

ESTIMATED COMPLETION

PROJECT INFORMATION

*Bald Mountain Road            (PERMIT PROJECT)

Dutton Road to Roxbury Drive (south of Silverbell Road)

Orion Township

Installation of an underground powerline.

Yes.

Dutton Rd to Squirrel Rd to Silverbell Rd, back to Bald Mountain Rd and vice versa.

Corby Energy Services, Inc. (on behalf of DTE)

4/10

5/7

Permit Work, Short-Term Work & Road Closures

*Clarkston Road (PERMIT PROJECT)

Adams Road to Lake George Road

Oakland Township

Drainage improvements, storm sewer installation and gravel road paving by private developers.

Yes. Residential and business access maintained throughout construction.

Lake George Rd to Stoney Creek Rd to Adams Rd, back to Clarkston Rd and vice versa.

Ajax Paving

4/10

Late June

Permit Work, Short-Term Work & Road Closures

East Avon Road (PERMIT PROJECT)

Avon Road to Dequindre Road

Rochester Hills and Shelby Township

Great Lakes Water Authority (GLWA) water infrastructure improvements. The project includes reconstruction and widening of East Avon Rd and roundabout construction at 23 Mile and Dequindre Rd.

Yes.

Dequindre Rd to Hamlin Rd to Ryan Rd to Shelby Rd to 24 Mile Rd, back to Dequindre Rd and vice versa.

GLWA

12/5/22

Mid-August

Great Lakes Water Authority

East Avon Road Dequindre Road and 23 Mile Road (PERMIT PROJECT)

23 Mile Road and Dequindre Road

Rochester Hills and Shelby Township

Great Lakes Water Authority (GLWA) water infrastructure improvements. The project includes reconstruction and widening of East Avon Rd and roundabout construction at 23 Mile and Dequindre Rd.

Yes.

Dequindre Rd to Hamlin Rd to Ryan Rd to Shelby Rd to 24 Mile Rd, back to Dequindre Rd and vice versa.

GLWA

3/20

Mid-August

Great Lakes Water Authority

Elizabeth Lake Road/ Teggerdine Road intersection (PHASE 1)

Elizabeth Lake Road/ Teggerdine Road intersection

White Lake Township

Single-lane roundabout construction with improved drainage, Americans with Disabilities Act-compliant crosswalks, sidewalks, asphalt paving at the roundabout, street lighting, installation of some curbs and gutters.

Yes, the intersection is closed to traffic.

Elizabeth Lake Rd to Pontiac Lake Rd to Highland Rd (M-59) to Bogie Lake Rd to Cooley Lake Rd to Oxbow Lake Rd, back to Elizabeth Lake Rd and vice versa.

Fonson Company Inc.

3/13

Early June

Elizabeth Lake Road Roundabouts (White Lake Township)

Elizabeth Lake Road/Oxbow Lake Road intersection (PHASE 2)

Elizabeth Lake Road/Oxbow Lake Road intersection and resurfacing work on Elizabeth Lake Road from Teggerdine Road to Oxbow Lake Road

White Lake Township

Single-lane roundabout construction with improved drainage, Americans with Disabilities Act-compliant crosswalks, sidewalks, asphalt paving at the roundabout, street lighting, resurfacing between the two roundabouts, curb and gutter installation.

Yes, the intersection will close to traffic once roundabout construction is completed at Elizabeth Lake Rd/Teggerdine Rd intersection and after school is out.

Elizabeth Lake Rd to Pontiac Lake Rd to Highland Rd (M-59) to Bogie Lake Rd to Cooley Lake Rd to Oxbow Lake Rd, back to Elizabeth Lake Rd and vice versa.

Fonson Company Inc.

June, TBA (after completion of the current school year and the roundabout construction at Elizabeth Lake Rd/Teggerdine Rd)

Early September

Elizabeth Lake Road Roundabouts (White Lake Township)

Fourteen Mile Road

Barrington Road to Dequindre Road

Madison Heights and Troy

Asphalt resurfacing, concrete repairs, minor drainage improvements, Americans with Disabilities Act-compliant crosswalks, traffic signal upgrades, repairs to curbs and gutters.

No, expect lane closures.

No.

Florence Cement

3/6

Mid-August

Fourteen Mile Road, Barrington to Dequindre Road

*Livernois Road (PERMIT PROJECT)

Northbound Livernois Road, Auburn Road to Hamlin Road (southbound Livernois Road will remain open to traffic)

Rochester Hills

Road widening and approach construction to facilitate private development.

Yes, northbound Livernois Rd will close to traffic on approximately 4/10. Southbound Livernois Rd will remain open to traffic.

Northbound Livernois Rd detour is Auburn Rd to Crooks Rd to Hamlin Rd, back to Livernois Rd.

East Edge Excavating on behalf of OKY Construction

4/10

4/25

Permit Work, Short-Term Work & Road Closures

Novi Road

Nine Mile Road to Ten Mile Road

Novi

Asphalt resurfacing, some widening, Americans with Disabilities Act-compliant crosswalks, culvert/sewer crossing replacements, drainage improvements, traffic signal upgrades, concrete replacement and left-turn lane extension south of 10 Mile Rd.

The road will remain open during concrete replacement at Novi/Ten Mile Rd intersection. The road will close for approximately 35 days for culvert replacements. Once complete, the road will only be open to southbound traffic for the project’s duration.

Yes, starting approximately April 24. Nine Mile Rd to Meadowbrook Rd to Ten Mile Rd, back to Novi Rd and vice versa. Residential and business access maintained.

Springline Excavating LLC

3/20

Late fall

Novi Road, Nine Mile to Ten Mile Road

Ten Mile Road (PHASE 1)

Haggerty Road to Meadowbrook Road (closure is just west of Bethany Way to just west of Nilan Drive)

Novi

Remove and replace the Bishop Creek culvert under Ten Mile Road, just west of Bethany Way.

Yes. Residential and business access maintained east and west of the culverts.

Novi Rd to Grand River Ave to Haggerty Rd, back to Ten Mile Rd and vice versa.

Toebe Construction

1/5

4/17 (approximate) The Ten Mile Road resurfacing project, Meadowbrook to Haggerty Road, will continue from the spring of 2023 through the fall.

Ten Mile Road

Ten Mile Road (PHASE 2)

Haggerty Road to Meadowbrook Road

Novi

Resurfacing with asphalt, safety improvements (continuous center left-turn lane), Americans with Disabilities Act-compliant crosswalks, sidewalk on the south side of Ten Mile Rd, traffic signal upgrades, shoulder widening, curb and gutter repairs/replacement.

Yes, the road will close to westbound traffic and remain open to eastbound traffic. Business and residential access maintained.

Westbound traffic detour is Haggerty Rd to Grand River Ave to Novi Rd, back to Ten Mile Rd.

Toebe Construction

4/17 (approximate)

Fall

Ten Mile Road

Twelve Mile Road (PERMIT PROJECT)

Dartmouth Road to Stephenson Hwy.

Madison Heights

MDOT is constructing a diverging diamond interchange in conjunction with I-75 construction, 8 Mile Rd (M-102) to north of 13 Mile Road.

Yes

12 Mile Rd to John Rd to 13 Mile Rd to Stephenson Hwy., back to 12 Mile Rd and vice versa.

MDOT

2/24

8/31

Modernize 75

Waldon Road (PERMIT PROJECT)

Baldwin Road to Clintonville Road

Independence Township and Orion Township

Utility relocation is being done before gravel road paving and roundabout construction at Waldon Road and Clintonville Road.

No, expect periodic lane closures with flaggers directing traffic.

No

Various utilities

3/6

TBA

Waldon Road, Clintonville to Baldwin Road

*indicates a new project; TBA (To Be Announced)

 

 

 

 