CONTRACTOR/TIMEFRAME/DETOUR:
CONTRACTOR: Superior Contracting
START DATE: August 1
END DATE: October 1
WATERFORD TOWNSHIP WATERMAIN RELOCATION START DATE: April 25
WATERMAIN RELOCATION COMPLETION: May 15
DETOUR (watermain relocation and culvert work): Cass Elizabeth Lake Road to Cooley Lake Road to Hiller Road, back to Cass Lake Road and vice versa. Residential and business access are maintained north and south of the culvert and watermain work.