Ten Mile Road, Meadowbrook Road to Haggerty Road (2022-23)

PROJECT LIMITS/COMMUNITY/FUNDING:

PROJECT LIMITS:  Meadowbrook Road to Haggerty Road

COMMUNITY:  City of Novi

FUNDING:  The estimated $9.6 million project is mostly paid for with federal road funding. The remaining costs are split between the Road Commission for Oakland County, City of Novi and Oakland County general government through the Tri-Party Program.  

PROJECT DESCRIPTION: 

PHASE I CONSTRUCTION (2022):

  • Repairing pavement at the Haggerty /Road/10 Mile Road intersection (Sept. 12 through Oct. 13, 2022  - complete)
  • Storm sewer work on Ten Mile Road, Haggerty Road to Meadowbrook Road (starting Oct. 19 through Jan. 2023; work will be done under lane closures and flaggers directing traffic) 
  • Tree removal (Oct. 1, 2022, through March 1, 2023)

PHASE II CONSTRUCTION (2023)

  • Milling (grinding off) the existing road surface
  • Repaving with asphalt and concrete (depending on the section of road) 
  • Removal and replacement of two culverts under the road starting January 5
  • Implementing safety improvements including a continuous, center left-turn lane; adding and extending selected right-turn and deceleration lanes  and widening the road shoulders
  • Repairing and replacing curbs and gutters 
  • Upgrading pedestrian crosswalks to comply with the Americans with Disabilities Act (ADA) 
  • Adding an eight-foot-wide sidewalk along the south side of this section of Ten Mile Road 
  • Upgrading traffic signals at 10 Mile/Meadowbrook and 10 Mile/Cranbrook intersections 
  • Watermain replacements (City of Novi work) 

CONTRACTOR:

CONTRACTOR:  Toebe Construction

CONTRACTOR WEBSITE: https://toebe-construction.com/

PROJECT TIMELINE/ROAD CLOSURE INFORMATION:


PROJECT START: Sept. 12, 2022  (concrete work in the Haggerty Road/Ten Mile Road intersection and storm sewer work on Ten Mile, Haggerty Road to Meadowbrook Road) COMPLETE

PHASE I CONSTRUCTION:

ROAD CLOSURE:  Ten Mile Road, Haggerty to Meadowbrook Road, is expected to close on  January 5, 2023, through May 22 for the replacement of two culverts under the road.  Access to residential and business properties maintained.  The Ingersol Creek culvert, just west of Nilan Drive,  will be removed and replaced first. The Bishop Creek culvert just west of Bethany Way will be removed and replaced after the work on the Ingersol Creek culvert is completed.  (Contractor changed the order of culvert replacements).

DETOUR FOR THROUGH TRAFFIC (during the culvert work): Novi Road to Grand River Avenue to Haggerty Road back to 10 Mile Road and vice versa.  Residential and business access maintained east and west of the culvert work.

PHASE 2 CONSTRUCTION:

SPRING OF 2023:  Expected to start May 31   May 22.

Westbound Ten Mile Road will close to through traffic.  Eastbound Ten Mile Road will remain open to traffic.

DETOUR FOR WESTBOUND TEN MILE TRAFFIC STARTING MAY  22: Haggerty Road to Grand River Avenue to Meadowbrook Road, back to Ten Mile Road.  The road is expected to reopen to eastbound and westbound traffic approximately mid-August.  

PROJECT EXPECTED COMPLETION:  Ten Mile Road is expected to reopen to traffic on September 18 25. 