Union Lake Road Culvert Replacement

UPDATE: Utility relocation is once again underway. Once complete, the culvert replacement project will begin; expect the road close starting April 25.

PROJECT LIMITS:   Culvert is located between Commerce and Wise roads, over the Hayes Creek (just north of Willow Road)

COMMUNITY:  Commerce Township

FUNDING:  The $778,000 project is funded by the Road Commission for Oakland County. 


PROJECT INCLUDES:

  • Culvert removal and replacement
  • Asphalt paving and new pavement markings over culvert
  • Concrete curbs and gutters
  • New guardrails
  • Upgraded traffic signal at the Willow Road/Union Lake Road intersection
  • Lake level control upgrade

CONTRACTOR:  VIL Construction of Sterling Heights

START DATE:  April 25, 2022 (expected closure) DELAYED DUE TO AT&T UTILITY RELOCATION WORK 

LANE CLOSURE:  June 20, 2022

FULL CLOSURE: July 28, 2022

END DATE: Late September 2022 

ROAD CLOSURE:  Yes. Residential, business and DNR boat launch access are maintained north and south of the culvert. 

DETOUR:  Wise Road to Carroll Lake Road to Commerce Road, back to Union Lake Road and vice versa.   