Maple/Middlebelt Road Roundabout 2019-2020
MAPLE/MIDDLEBELT ROAD ROUNDABOUT CONSTRUCTION CONTINUES IN 2020
East and west legs of Maple Road at Middlebelt Road will close. Northbound and southbound Middlebelt Road will remain open to traffic; however, there will be no access to eastbound and westbound Maple Road. The closure of Maple Road at Middlebelt will take place on Monday, April 27 through late June.
PUBLIC MEETING: The RCOC will hold a public meeting regarding the project on November 13, 2018 from 4 p.m.-7 p.m. at the Orchard Lake Middle School, 6000 Orchard Lake Road, West Bloomfield
Project Limits: Maple Road and Middlebelt Road intersection and culvert replacement east of Middlebelt Road
Community: West Bloomfield Township
Funding: The approximately $6.6 million safety improvement project is funded with a mix of federal and local dollars. Local funding is shared by Road Commission for Oakland County, West Bloomfield Township and Oakland County general government through the Tri-Party Program.
Project details:
Construction of a roundabout at the Maple/Middlebelt intersectionDrainage improvementsAmericans with Disability Act (ADA) compliant crosswalks with High-intensity Activated cross-WalK beacon (HAWK) (2020)Roundabout concrete work (2020)Water main replacementsCulvert removal and replacement on Maple Road east of Middlebelt Road (scheduled to begin in June); culvert is located between Glenway Drive and Bloomfield Glens RoadBehind the curb restoration (2020)Permanent street lighting (2020)
Detour: Yes, for 2020 continued construction is expected to begin March 30. East and west legs of Maple/Middlebelt will close. Northbound and southbound Middlebelt Road will remain open to traffic; however, there will be no access to eastbound and westbound Maple Road.
Detour information:
- East leg of Maple Road at Middlebelt Road detour is Inkster Road to Walnut Lake Road, back to Maple Road.
- West leg of Maple Road at Middlebelt Road detour is Walnut Lake Road to Orchard Lake Road, back to Maple Road
Contractor: Angelo Iafrate
Expected 2020 construction start: March 30 April 15 MONDAY, APRIL 27, 2020
Expected 2020 completion: June 19, 2020 open to traffic
Roundabout expected completion: Late fall (weather-dependent) ROUNDABOUT OPEN TO TRAFFIC ON 12/12/19 (further work scheduled for 2020)
Roundabout resources: CLICK HERE
QUESTIONS? Call 877-858-4804 or email us: dcsmail@rcoc.org
Middlebelt east of Maple Road culvert replacement Work Zone Camera: CLICK HERE
Maple/Middlebelt Road roundabout construction Work Zone Camera: CLICK HERE
View Progress Photos: Maple/Middlebelt Culvert Replacement & Roundabout Construction Progress Photos