Davisburg Road Culvert Replacement 2020


Project Limits: 
Garner Drain located between Oakhurst Road and Terrace Road (located between Carol Ridge and West Braemar/Erindale Ct.)

  • Community: Rose/Springfield Townships
  • Comments: Culvert replacement on Davisburg Road over the Garner Drain
  • Project cost:  Construction cost is $845,000 with $502,000 funded through Federal Aid with remaining portion from the Road Commission for Oakland County.  
  • Project details:  
 Remove and replace culvert under the road
 New asphalt pavement and lane marking over culvert
 New guardrail

  • Contractor: Aielli Construction Company
  • Contractor website:  CLICK HEREto learn more about Contractor website
  • Start Date:  July 31 (expected start)
  • End Date:  Early October  Nov. 2
  • Detour: Yes
  • Detour Route:  Milford Road to White Lake Road to Ormond Road, back to Davisburg Road and vice versa.