Project limits: Over Teeple Creek, east of Duck Lake Road (culvert is located east of Teeple Creek Lane)
Communities: Commerce and White Lake townships
Estimated project cost and funding sources: The $670,000 project is funded by the R.C.O.C.
Construction information:
- Remove and replace culvert under the road
- Replace guard rail
- Pave area with asphalt
Project start: August 3 AUGUST 10
Project completion: Late September October 16 - OPEN TO TRAFFIC
Contractor: DiPonio Constracting, Inc.
Contractor website: http://diponiocontracting.com/
Detour: Yes
Detour: South Duck Lake Road to Commerce Road to Carey Road, back to Cooley Lake Road and vice versa.
ADDITIONAL INFORMATION:
Cooley Lake culvert replacement photos: CLICK HERE
Cooley Lake Road to close west of Ford Road on the White Lake/Commerce township border for culvert replacement (revised start date)