Mason Street - 2019

Community:  Rose Township

Project limits:  Milford Road to Mason Street

Project funding:  Provided by Rose Township through Tri-Party funding provided by Oakland County general government   

Project cost:  $171, 000

Project description:  Paving the gravel road with some drainage improvements 

Contractor:  Fonson Construction

Start date:  June 8

End date:  Mid-July COMPLETE

Detour:   Yes for through traffic; residential and township hall traffic will be maintained.  

Detour Route:  The detour is Franklin Street to Clinton Street, back to Mason Street and vice versa