Project location: Milford Road over the Shiawassee River just east of South Fenton Road (east of railroad tracks)
Community: Rose Township
Project description:
Project cost: $850,000
Contractor: Zito Construction
Contractor Information
Project start: September 16, 2019 September 19, 2019 (moved by the contractor)
Project completion: November 13
Detour: Yes, residential access will be maintained east of culvert
Detour route: Milford Road to Clyde Road to Hickory Ridge Road to Fenton Road, back to Milford Road and vice versa
Milford Road east of Fenton Road in Rose Township to close Sept. 16 Sept. 19 through mid-October late October for culvert removal and replacement (date change by contractor, updated 9/17/19)