Project limits: Clarkston Road to Heights Road
Community: Orion Township
Project cost: $687,566 funded by the RCOC, Orion Township and Tri-Party Program funds provided by Oakland County General Government
Project details:
Contractor: Cadillac Asphalt
Start date: August 6, 2018
End date: Open to traffic on October 19
Detour: Yes, for through traffic (residential access will be maintained
Detour route: Clarkston Road to Joslyn Road to Heights Road, back to Pine Tree Road and vice versa
Pine Tree Road Detour Map: Click Here
Photo Gallery: Pine Tree Road
Pine Tree Road closure to begin August 6 through mid-September