Livernois Road

  • Project limits:   Big Beaver Road to Maple Road
  • Community:  Troy
  • Project cost:  $580,047 funded by the RCOC, City of Troy and Tri-Party Program through the Oakland County General Goverment
  • Planned work:
    • Milling and resurfacing from Maple Road to the I-75 overpass
    • Concrete repairs from the I-75 overpass to Big Beaver
    • Two-way traffic will be maintained throughout the project
  • Contractor:  Cadillac Asphalt
  • Project start: Tuesday, August 7
  • Project anticipated completion: mid-September  COMPLETE
  • Detour:  No, however, traffic will be reduced to one lane in each direction with a center left-turn lane remaining open.