Funding: The $2,092,740 project is mostly funded utilizing federal dollars with the RCOC providing $418,548
Project details:
Adams Road will be milled and resurfaced under traffic from South Blvd to Square Lake Road
Adams Road from Square Lake Road to South Blvd will be milled and resurfaced; during work only northbound Adams Road will remain open to traffic
Project also includes shoulder widening, drainage improvements and Americans with Disabilities Act compliant sidewalks and pedestrian signals
Contractor: Ajax
Start Date: August 8, 2018
End Date: November 30, 2018, open to traffic (miscellaneous work remains)
Detour: Yes for southbound Adams Road, northbound Adams Road will remain open to traffic Southbound Adams is closed just north of the I-75 freeway ramps (near Charnwood Drive).
Detour route: For southbound Adams Road traffic is South Blvd to Squirrel Road to Square Lake Road, back to Adams