$2.3 million project is funded by the RCOC, Groveland Township and Oakland County general government through its Tri-Party Program
Complete reconstruction
Installation of curb and gutter
Shoulder widening
Improved drainage
Replacement of the Thread Creek culvert
Tree removal in the right of way begins Feb. 13, 2018; with traffic under flag control when necessary. Trees are removed in the winter per federal guidelines that protect the Northern Long-eared Bat and the Indiana Bat, both are on the national endangered species list. Trees need to removed by March 31. Tree trunks and stumps will be removed when the project starts in the summer of 2018. Utility work is also on-going in anticipation of the project.
Contractor: Angelo Iarate
Start Date: July 30, 2018
End Date: Late November
Detour: Yes, Dixie Hwy to Grange Hall Road back to Trip Road and vice versa (residential access maintained throughout the project)