Currie Road

PROJECT INFORMATION: 

PROJECT LIMITS:  Eight Mile Road to just north of Nine Mile Road

COMMUNITY:  Lyon Township

PROJECT INFORMATION/FUNDING/TIMELINE/CONTRACTOR/DETOUR:

Project funding:  The approximate $4.4 million project is funded by federal dollars, Lyon Township and the Road Commission for Oakland County. The project also includes a 5-year Local Agency Program warranty.  

Project flier:  CLICK HERE

Start:  April 4, 2022; road closures to start on April 15  , April 18

Approximate Completion:  Mid-October 2022

Project includes:

  • Asphalt paving
  • Construction of a compact roundabout at Currie Road and Nine Mile Road
  • Construction of a single lane roundabout at Currie Road and Eight Mile Road
  • Construction of concrete curbs and gutters
  • Drainage improvements
  • New pavement markings
  • New signage  

Phase II Contractor: Iafrate Construction

Detours:

Currie Road traffic detour: Ten Mile Road to Napier Road to Seven Mile Road, back to Currie Road.

Eight Mile Road detour: Griswold Road to Ten Mile Road to Napier Road, back to Eight Mile Road and vice versa. 

Residential access on Currie Road will be maintained. Residents will need to access Currie Road from Nine Mile Road during the roundabout construction at Eight Mile Road and Currie Road is completed in late June. The roundabout construction will completely close the Eight Mile/Currie Road intersection. 

Photos:

To view photos of Phase 1 (9 Mile to 10 Mile Road ) of the Currie Road project: CLICK HERE

Preparing Currie Road for Paving from 9 Mile Road to 10 Mile Road

To view photos of Phase 2 of the Currie Road project: CLICK HERE

8 Mile Road and Currie Road intersection street sign.