Project description:

This project involves the paving of the currently gravel section of Currie Road from 8 Mile Road to 10 Mile Road in Lyon Township over a several-year period including the construction of roundabouts at the Currie/8 Mile and Currie/9 Mile intersections. 

Phase I and Phase II:

2020 work includes utility relocation and tree removal.  

PHASE I (500 feet north of 9 Mile Road to 10 Mile Road)

Start:  TBA
Approximate Completion:  TBA

  • Asphalt Paving
  • Intersection improvements at Currie Road and 10 Mile Road
  • Improvements to roadway drainage
  • Construction of curb and gutters
Currie Road will be closed to through traffic. The detour is 9 Mile Road to Napier Road to 10 Mile Road, back to Currie Road and vice versa. Tree removal and utility relocation will take place in 2020. Paving will occur in 2021.

PHASE II (500 feet north of 9 Mile Road to 8 Mile Road)

Start: TBA
Approximate Completion: TBA

  • Asphalt paving
  • Construction of a compact roundabout at Currie Road and 9 Mile Road
  • Construction of a single lane roundabout at Currie Road and 8 Mile Road
  • Improvements to roadway drainage
  • Construction of curb and gutters

Contractor:  TBA

Detour:   Currie Road will be closed to through traffic. The detour is 8 Mile Road to Napier Road to 10 Mile Road, back to Currie Road and vice versa

ADDITIONAL INFORMATION:


Project Info Flier

Project Meeting Flier

Public Information Meeting Press Release

The Oakland Press Article on Currie Road Paving (10/21/2019)

WHMI Article on Currie Road Paving Informational Meeting (10/23/2019)